Ask Experts Questions for FREE Help !
Ask
    bbenes's Avatar
    bbenes Posts: 2, Reputation: 1
    New Member
     
    #1

    Jan 19, 2009, 04:57 PM
    Leveling a concrete floor
    I have a monolithic concrete floor (in Texas) and I need to level the concrete where I've enclosed a patio. The deepest edge will be about 3" and the shallow edge will be about 1". It is all interior and I'll be putting a tile floor on top. What type of concrete and what type of tie in or mesh (if any) should I use?
    21boat's Avatar
    21boat Posts: 2,441, Reputation: 212
    Ultra Member
     
    #2

    Jan 19, 2009, 07:58 PM

    What are the temperature changes in your region and I need to know that for expansion rates in the crete it will help me direct you in the right direction.

    Do you have concrete experiences ?

    The reason I'm asking is the word used here "Monolithic" I'm am a professional Crete Contractor. In all 35 years of the trades I never heard a home owner use that term unless they read it out of a book or it's a test question or you're a Crete person in the trades. So let me know the level you are at and that would GREATLY help me determine the best way for you to accomplish this task and your skill Level.
    Example I can tell you what Psi Crete to use and the slump to re pour it and the amount of Crete and tell you how to wet bench it.
    Thank You
    I will be waiting to help! And get you on your way.
    bbenes's Avatar
    bbenes Posts: 2, Reputation: 1
    New Member
     
    #3

    Jan 20, 2009, 05:51 PM
    I don't have any concrete experience. I've done some GC work, mostly fire restoration. The framer who built the room ( a friend) used that term to describe the pour as one complete slab. We were concerned about shifting of two slabs before the work started.

    So I have a solid understanding of construction, but really don't understand concrete. I've mortared a little stone area, but that's about it.

    Thanks for your help. I can send a picture if will help out.

    As far as temp in the area, I'm in Fort Worth TX. Annual temp range is from 10 to 100. We're approaching spring so our daily change is 30 - 40 at night to 60 - 70 in the day. This area is all heated interior.

    I appreciate your help.

    Bruce
    concretejack's Avatar
    concretejack Posts: 2, Reputation: 1
    New Member
     
    #4

    Mar 8, 2011, 08:13 PM
    Contact a slabjacking contractor. If the slab has settled 1 to 3 inches, there are definitely instability problems below the slab that need to be address (most likely voids that will allow the concrete slab to continue to settle) and if they aren't resolved, no amount of work on the surface will correct the problem. Check out www.ConcreteJack.com to learn more about the slabjacking process; it works by injecting either grout or polyurethane foam under the slab to fill voids and relevel the concrete, and most contractors will warranty their work.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Concrete floor leveling issue [ 1 Answers ]

I need help/advice/hints/any ideas that will help me solving my concrete leveling problem, when trying to achieve a leveled surface before installing wood floor. After pouring the self-leveler (on concrete substrate) one area at a time as I can mix only one bucket at a time, I now have different...

Leveling concrete floor beneath toilet [ 3 Answers ]

First tme site user needs help determining the best way to make a level pad underneath a basement floor toilet. The old existing toilet was mounted on a 4" cast iron pipe (so the pipe shoulder was actually a 5" opening). The toilet had a ton of plumbers putty instead of a wax ring. I stuck a...

Leveling concrete floor [ 4 Answers ]

We are attempting a bathroom installation. We would like to lay tile, but the concrete floor is uneven. We had a friend use an auto leveler to float the floor, but it still came out uneven. We then tried again pouring it over the entire floor. It is still uneven. We have marked out the low...

Leveling a concrete floor [ 5 Answers ]

I have a 12' x 12' concrete floor that was poured a bag at a time and has about a 2" high spot. The floor was worked too much and is far from smooth. What is the best and easiest way to level this floor? thanks