Ask Experts Questions for FREE Help !
Ask
    paul0317's Avatar
    paul0317 Posts: 4, Reputation: 1
    New Member
     
    #1

    Jul 10, 2011, 12:19 AM
    dowels in new concrete
    I am pouring a new slab for my RV. It will be outside in a covered shed. The slab is 40' X 50' 6" deep. My queston is can I put the Dowels in place before I pour and not have to drill them. I have 6 areas to pour and breaking it up into 2 pours 3 sections each day.
    parttime's Avatar
    parttime Posts: 1,440, Reputation: 113
    Ultra Member
     
    #2

    Jul 10, 2011, 03:57 AM

    Hi paul and welcome to AMHD, when you say "dowels" if you mean rebar to tie the sections together? Then yes you can install it first. Good luck
    hkstroud's Avatar
    hkstroud Posts: 11,929, Reputation: 899
    Home Improvement & Construction Expert
     
    #3

    Jul 10, 2011, 07:11 AM

    Are you talking about installing anchor bolts or straps for the wall plates?
    paul0317's Avatar
    paul0317 Posts: 4, Reputation: 1
    New Member
     
    #4

    Jul 11, 2011, 05:54 PM
    Comment on parttime's post
    Thanks for the response. I am new to this and learning. The concrete slabs are separate and I was going to tie them together and allow for expansion with out cracks. I found that you could drill one side and put rebar and then pour other slab. I think that allows the slab to contract with out moving. I was wondering if I could put the dowels in before I poured.
    I am not even sure this is needed. Is just using the rebar for expansion joint sufficient for decreasing cracks. I am probably over thinking this.
    smearcase's Avatar
    smearcase Posts: 2,392, Reputation: 316
    Ultra Member
     
    #5

    Jul 11, 2011, 07:41 PM

    These smooth dowel types of joints have been used in highway concrete paving at contraction joints (every approx. 40 feet measured in the direction the vehicle travels) for a long time and were referred to as load transfer devices. They were normally placed at mid-point of the depth and supported on chairs (metal supports holding them in correct position-the chairs being embedded with the pour. Usually, both sides of the joint were placed in the same operation (continuous) and a joint sawed within about 12 hours max.
    If you are just pouring one side of the joint per pour, you could probably build a wooden support sitting on the grade of the second pour, then remove for 2nd pour. The smooth dowels are usually greased to increase movement.
    Dr1757's Avatar
    Dr1757 Posts: 186, Reputation: 25
    Junior Member
     
    #6

    Jul 13, 2011, 04:07 PM
    Paul over time all concrete is going to crack no matter what precautions or methods you use. Anytime I have added a concrete slab next to an existing slab I always drill 3/4 holes with a hammer drill and drove in pieces of rebar a foot long (6 inches into the old slab). This will tie the sections together and keep them level, and prevent separation.

    If I were in your place I would pour it all at once and have expansion joints cut across it every 20 feet.

    Hope this helps
    paul0317's Avatar
    paul0317 Posts: 4, Reputation: 1
    New Member
     
    #7

    Jul 14, 2011, 12:02 AM
    Comment on Dr1757's post
    Yes I am pouring smaller section to be able to handle it with two people. I am adding a board to separate the pours for expansion. I was just reading and found out about the dowels. Never could find them at the Box stores so thinking I might make my own using pipe and rebar with grease in between. I am more concerned with moving up and down then side to side. The dowels sound like they would help with both.
    Any comments on my home make dowel working or being a waste of time.
    Need to change my name to the “weekend carpenter”.
    Dr1757's Avatar
    Dr1757 Posts: 186, Reputation: 25
    Junior Member
     
    #8

    Jul 14, 2011, 03:11 AM
    The last slab I poured was 20' wide by 28' long using the 3/4 inch rebar at two foot intervals to tie it to the adjoining slab. I dug 24" deep footers and one 24" deep beam which ran length wise. This was 4 years ago and this addition has not moved. There have been some surface cracking which is normal but nothing serious. I don't think your going to accomplish much by using pipe and rebar to make a sliding connection. I would not use wood between your sections, it will rot away then you'll have fill the gap with some sort of filler. If you've never poured concrete before I would highly recommend having some experienced help, or spend the money and hire someone to do it for you.
    paul0317's Avatar
    paul0317 Posts: 4, Reputation: 1
    New Member
     
    #9

    Jul 16, 2011, 11:03 PM
    Comment on Dr1757's post
    I should have been more clear with the use of board. I am using fiber board, I think it's called, to separate. Thanks for the help all. Not done building so might ask more.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Extending a concrete slab patio using concrete blocks [ 11 Answers ]

I currently have a 14x16 concrete patio I am about to build a pergola over and have also decided to lay stone tiles over the concrete instead of staining it to give it a new look. I was looking at my plans and realized this would be a perfect opportunity to extend my patio out another 5ft so it...

How do I lay concrete over concrete to avoid chipping, flaking and cracking? [ 4 Answers ]

I am considering overlaying concrete over concrete in the basement. How can I best do this to avoid problems with it in the future. I plan on coloring the cement before I say or staining it once it has been overlayed. I want to do it right the first time. Thanks

Interior concrete floors over the existing concrete slab [ 4 Answers ]

Can you put an interior decorative concrete floor over an existing concrete slab that now is carpeted

How many bags of ready mix concrete to make 1 1/2 yards of concrete? [ 2 Answers ]

How many 80lb bags of ready mix concrete do I need to make a yard and half

Installing a concrete shower floor over a custom concrete pan. [ 4 Answers ]

I want to install a stained concrete shower floor instead of tile. I have already installed a custom shower pan and pitched it to specs. My question is should I be concerned about the new floor cracking since it will only be 1/2" thick? If you have any other suggestions on the install, please...


View more questions Search