Ask Experts Questions for FREE Help !
Ask
    carho3's Avatar
    carho3 Posts: 1, Reputation: 1
    New Member
     
    #1

    Nov 7, 2010, 07:15 PM
    They use a job order system & apply overhead base on percentage of direct labour cost
    Work in Process Inventory account during March are given below.

    Work in Process

    Beginning Balance 0 Transferred out 240,000
    Direct Materials 45,000
    Direct Labour 75,000
    Overhead 225,000

    Ending Balance 105,000

    Only Job # 007 was still in process at the end of March and this job had been charged with $15,000 in direct material cost.

    a)How do I calculate the amount of direct materials cost charged to completed jobs during March.
    b) How do I calculate the predetermined overhead application rate at Trinco. (2 marks) =

    Answer = 225000/75000=3 (Is this correct?)

    c) What is the journal entry which accounts for the $240,000 transferred out of work in process inventory?

    Please I need help...

Check out some similar questions!

Job-order cost system [ 1 Answers ]

The following information applies to Job 730 completed by Ritter Manufacturing Company during October 2005. The amount of labor cost for the job was $67,350. Applied overhead amounted to $96,000. The project was completed and delivered to Lancer Company at a contract price of $285,000. Ritter...

Calculate the total cost of the job using direct labor hours as the allocation base? [ 0 Answers ]

ABC Corporation manufactured a new electronic part for Apple’s new cell phone. In particular, it manufactured 100,000 of these parts for Apple’s order. ABC wants to calculate the job cost and the cost per part. For this particular job, direct materials were $250,000 and direct labor was...

Job order cost & process cost system [ 0 Answers ]

Discuss the similarities and differences between job order cost and process cost systems


View more questions Search
 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.