They use a job order system & apply overhead base on percentage of direct labour cost
Work in Process Inventory account during March are given below.
Work in Process
Beginning Balance 0 Transferred out 240,000
Direct Materials 45,000
Direct Labour 75,000
Overhead 225,000
Ending Balance 105,000
Only Job # 007 was still in process at the end of March and this job had been charged with $15,000 in direct material cost.
a)How do I calculate the amount of direct materials cost charged to completed jobs during March.
b) How do I calculate the predetermined overhead application rate at Trinco. (2 marks) =
Answer = 225000/75000=3 (Is this correct?)
c) What is the journal entry which accounts for the $240,000 transferred out of work in process inventory?
Please I need help...