    Stand alone shower drain installation
    When installing a stand alone shower drain, is the drain attached to the cement, the floor board, or something else and how high does it need to be placed so I can make it even with the tiles?
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #2

    Nov 2, 2008, 02:52 PM
    Quote Originally Posted by sherrybrt View Post
    When installing a stand alone shower drain, is the drain attached to the cement, the floor board, or something else and how high does it need to be placed so I can make it even with the tiles?
    Are you building a custom tile shower or installing a manufactured shower base and enclosure? I ask because the drains will be different. You speak of both a cement floor and then a "floor board". Please explain. In short I need more details before I can answer. Is the drainage and water in place? Plese explain what you wish to accomplish. Regards, tom
    sherrybrt's Avatar
    sherrybrt Posts: 3, Reputation: 1
    New Member
     
    #3

    Nov 2, 2008, 03:59 PM

    This is a custom shower. There is a floor board with cement board on top of the floor board. Drainage and water is in place (an old tub was there before). Should the drain be attached to the wood floor board? The cement board? And how high?
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #4

    Nov 2, 2008, 04:08 PM
    Quote Originally Posted by sherrybrt View Post
    This is a custom shower. There is a floor board with cement board on top of the floor board. Drainage and water is in place (an old tub was there before). Should the drain be attached to the wood floor board? the cement board? and how high?
    Not so fast. You will have to install a flange type shower drain,(see image) before anything's done. This will install on the cement board and a shower pan will install to that. Since I don't even know what material the trap and raiser are This is about as much as I can tell you. Do you need instructions on how to form a shower pan and build a custom tile shower? Regards, tom
    sherrybrt's Avatar
    sherrybrt Posts: 3, Reputation: 1
    New Member
     
    #5

    Nov 2, 2008, 04:12 PM

    Thanks Tom... This was very helpful.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Stand up Shower Drain Connection [ 7 Answers ]

I have a Lasco shower unit. I'm installing it in the basement on concrete. I have a 2 inch PVC pipe extending out of the floor. How much pipe do I leave above the floor? Most of all is if I buy a Oatley connector, after I secure it to the shower itself, do I just slip the shower unit over the...

Trying to Install a basement stand up shower drain, need assistance? [ 2 Answers ]

Hi all, Just got a question, I am attempting to install my stand up shower(MAXX), drain, I have a 2" PVC pipe coming out from the basment concrete floor. When I put the drain on to the base of the shower and lay it on the desired location it dosen't sit flat because of the bottom part of the drain...

Stand up shower drain leakes [ 4 Answers ]

Our stand up shower in our bedroom leaks by the drain, we took out the old drain and replaced it w/a new one but it still leaks. Please help...

PVC Shower Pan Drain Installation [ 2 Answers ]

I'm installing a 36" x 36" PVC shower pan in a 2nd floor bath. I have a two piece shower drain where the bottom piece is glued to the 2" PVC waste line. It appears that I'm to glue the bottom piece flush with the subfloor, lay in the pan, and screw down the top of the drain (w/ rubber gasket). ...

Shower Drain Installation [ 3 Answers ]

As part of a remodeling effort, we are having a tiled shower built in our guest bathroom. We had a plumber come out to run the water and drain lines. He installed the drain. Last night I noticed that the hole he cut in the plywood sub flooring is quite a bit larger than the drain, so that...


View more questions Search