    Janelle Construction uses the completed-contract method for long term construction contract. The information for a specific contract as of Jan 1 2007:

    Cost incurred to date... $700,000
    Contract price... $2,000,000
    Estimated remaining cost to complete... $800,000

    $600,000 of cost was incurred during 2007 and on Dec 31, 2007 the estimated remaining cost to complete was still $800,000. The correct balance for the Construction in Progress at Dec 31, 2007.

    This is my working: 2,000,000 - 600,000 - 700,000 = 700,000
    Peachey's Avatar
    Peachey Posts: 99, Reputation: 1
    Junior Member
     
    #2

    Jul 12, 2009, 02:31 PM

    Am I correct?
    morgaine300's Avatar
    morgaine300 Posts: 6,561, Reputation: 276
    Uber Member
     
    #3

    Jul 13, 2009, 04:24 PM

    Posting again really isn't going to help - anyone who reads this knows you want to know if you're correct.

    Construction contracts is something I don't get into, so I can't answer. And sometimes we can't, which is why you don't hear anything - it's not necessarily because you're being ignored.
    Peachey's Avatar
    Peachey Posts: 99, Reputation: 1
    Junior Member
     
    #4

    Jul 13, 2009, 04:30 PM

    Sorry I forgot I posted it, because we got a lot of new leaflets to workout and with you help I got out a lot of them. Thank you anyway.
    paraclete's Avatar
    paraclete Posts: 2,706, Reputation: 173
    Ultra Member
     
    #5

    Jul 13, 2009, 09:16 PM
    You have arrived at the right answer by the wrong means the answer is 700000 because this is the amount actually expended
    morgaine300's Avatar
    morgaine300 Posts: 6,561, Reputation: 276
    Uber Member
     
    #6

    Jul 13, 2009, 10:24 PM
    Quote Originally Posted by paraclete View Post
    You have arrived at the right answer by the wrong means the answer is 700000 because this is the amount actually expended
    But if Construction in Progress is some type of asset account (like Work in Process for manufacturing), then there's both costs of 700,000 as of 1/1/07 (incurred prior to that point in time), plus another 600,000 incurred during 2007. 1,300,000 total.

    As I said, I don't know construction methods, but assuming Construction in Progress isn't an expense account (which would be only 600,000 for 2007), and is the "actual amount expended" as you said, there'd be a total of 1,300,000 in there, right?
    ArcSine's Avatar
    ArcSine Posts: 969, Reputation: 106
    Senior Member
     
    #7

    Jul 14, 2009, 06:10 AM
    I agree with morgaine300... I think the key is in Peachey's opening line that the completed contract method is being used here. With the CC method for long-term contracts (as opposed to percentage-of-completion), the construction costs are simply accumulated on the balance sheet until the contract is completed and closed.

    Upon completion, all the revenue is recognized, and all of the accumulated costs are then transferred from the Bal Sheet to the PnL as a cost-of-sale item.

    The statement that there are costs remaining to be incurred as of 2007 Dec 31 cinches it that the project hasn't yet completed. I'd think that as of that date the Bal Sheet should have an asset Construction In Progress standing at $1.3M, as morgaine300 said.

    Best of luck, Peachey... I hope that helped a bit.
    Peachey's Avatar
    Peachey Posts: 99, Reputation: 1
    Junior Member
     
    #8

    Jul 14, 2009, 06:30 AM

    Thank you a lot and thanks for the explanation.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Timelimit for incurred bills [ 1 Answers ]

How long do you have before your bankruptcy is discharged to include charges in your bankruptcy.. I have a bill from the date of my first hearing with the court. Can this bill be added to my bankruptcy

Ex trying to charge me for expenses incurred during the relationship [ 11 Answers ]

Good afternoon, I'm wondering how long someone has to bring up charges they feel are owed to them. My ex boyfriend claims I owe him money for various small charges amounting to $1200 from March (ish) 2006. I paid him back for anything that was owed during the relationship, but he's trying to...

Budget Percentage Costs That Might Be Incurred By a Small Restaurant [ 1 Answers ]

I am taking over an established a 50.s style diner that the owner is retiring from, I would like to know the budget percentages for costs related to this type of small restaurant

Credit card debt incurred overseas [ 2 Answers ]

Hi, I was issued an AMEX and VISA card while I was living overseas (the U.K). I returned to the US about 6 years ago and kept the cards active. It turns out that I owe AMEX about $6000 and last night I received a call from what I assume is an American collection agency. Can this debt...


View more questions Search