New Member
|
|
Mar 20, 2009, 03:07 PM
|
|
Concrete Patio Cracks After 5 Months
We had a large concrete patio laid in November 2008. Over the winter, it developed numerous cracks. The contractor insists it was poured correctly and that the cracks were caused by the frost from a cold winter. Is this possible? We are so disappointed.
|
|
 |
Ultra Member
|
|
Mar 20, 2009, 03:18 PM
|
|
What was the temperature outside when it was poured?
|
|
 |
Ultra Member
|
|
Mar 20, 2009, 03:19 PM
|
|
|
|
 |
Ultra Member
|
|
Mar 20, 2009, 03:24 PM
|
|
Could be the complete truth. My thoughts here is what was done in the prep for crushed stone under the concrete.
My other thought here is how could was it after it was poured and how much time went by before it froze?
Personally I cover ALL ground level pours if frost is or will be present. I give it a week and a half before I uncover. Also I do a gradual uncover to let the new concrete adjust to the quicker temp change. Use plastic and straw and concrete warming blankets to cover and adjust
If you could give me some more details I may tell you why it was more prone to crack. Its been a hard winter for many people and its played havoc on old concrete and New concrete is very susceptible.
Signed 21 Boat
If I Helped To Answer Your Question Please Rate My Answer
|
|
 |
New Member
|
|
Mar 20, 2009, 03:54 PM
|
|
21Boat - So you think we are just screwed? There is no way for me to "prove" they did anything wrong. The base passed city inspections, etc. It's just such a joke that we paid $5,000 for a patio full of cracks. Didn't even get to enjoy it for one summer. Any suggestions?
|
|
 |
Ultra Member
|
|
Mar 20, 2009, 09:59 PM
|
|
I HATE saying this but you are probably screwed.
Even though the base passed inspection doesn't mean it was correct. Concrete slabs are so under inspected in residential
The only way you would get close to a blame here is the temperature record of the days following the actual pour. If that dipped to or below frost then you have a case to present.
Concrete takes a week or so to cure enough to reach 65 to 70%+ at 70 degrees and up.
When its poured at 50 or 40 degrees this exponentially changes the curing time which in turn means longer cover for the concrete not to move in less strength days.
Other wise the percentage of a chance for it to crack greatly increases.
|
|
Question Tools |
Search this Question |
|
|
Add your answer here.
Check out some similar questions!
Fixing small cracks in concrete
[ 2 Answers ]
I'm getting ready to epoxy a concrete porch floor and the concrete has 4 cracks none more than 1/16" wide and the longest is approximately 10' slab is 4" + thick can I epoxy over these or do I need a filler and if so what do you recommend, I want to use a floor leveler as there are 3 bird baths ...
Poured Concrete Steps on Concrete Patio
[ 1 Answers ]
Hello,
I recently had a large portion of my driveway torn out/replaced, a 12 x 18 patio poured, and 3 half moons steps poured, all of 6 bag mix concrete.
The flatwork looks great, virtually flawless.
The steps, on the other hand, don't.
After removing the forms/frame for the three...
Concrete floor base cracks
[ 12 Answers ]
I am considering purchasing a house and in one room there is a cement crack about 3 feet long. The house is 4 years old and has a cement base under the carpeting and tile. I contacted a cement pourer who said this was a fairly ordinary occurrence and should not pose a problem. Is this a...
Cracks in concrete foundation
[ 2 Answers ]
I recently inherited my grandparents home. It is probably 65 years old with a concrete foundation and crawl space underneath. It was built on to about 45 years ago. The older part of the house has several cracks in the outside concrete foundation. I don't know if they are recent or have been...
Concrete cracks
[ 1 Answers ]
I have cracks in a side path I poured at my home. Is it possible for shrinkage cracks to look like settlement cracks? I compacted all the subgrade first, and took every precaution to ensure I did not get settlement cracks, i.e.. Adequate depth to reinforcing and not a slumpy concrete, but I still...
View more questions
Search
|