Sep 3, 2008, 10:35 AM
|
|
Hey mark,
I will get that pilot bit... :)
With the shower, how do I know once I assemble it and morter in in that I'm getting a water tight seal? Is there any way to really test it?
I'm thinking pour some water in the pan, but then when I take it apart and look, if there is any water on the inside of the drain it will drip down... or no?
|
|
 |
Senior Plumbing Expert
|
|
Sep 3, 2008, 12:45 PM
|
|
Hey hey..
You will dry fit the base first and cut pipe down so it is about 2 inches higher than needed.
Play with it and examine how much tilt will be needed to achieve a plumb base from side to side and from front to back. How much do you have to raise each side to achieve perfect plumb? Make note of it on left and then on right sides of wall. Then you want to take a pencil and trace the level base where it is perfect.
Now is a good time to dry fit the donut at the drain and mark the pipe for cutting. If super confident in all this then you can cut the pipe to the right height, but be sure to study the drain with piece of pipe in it first by playing with drain and pipe and the brass ring to tighten it (remember to tie a string onto the flat wrench).
Now, examine the base and with information gained from above determine how much mortar you will need to set the base. You want base plus lift needed to level base plus an inch or so extra to squeeze out to edges. Then install mortar so that it is about 4 to 6 inches away from the center of the base (so won't squeeze up through drain hole) and set the base to match the pencil line on the wall.
Double check with the level and then screw the base to the studs. Don't be afraid to set temporary shims from front to help support the front of the base while base mortar dries (front has a tendency to drop overnight so shim this). Then, before mortar sets, install the drain as required... install pre-soaped rubber donut, then install ring, then tighten appropriately. Then pour 1/2 gallon of water into drain (not in pan... just into pipe to reduce sewer gasses from coming up). Then snap cover over drain. Do all this without moving/falling into base... ;)
Let base dry overnight and then set walls according to instructions. If mortar happens to squeeze into drain area just take a pencil and thin rag and remove propmtly.. then proceed.
You should not really need to test the drain at this stage if you do all this correctly... study the drain with piece of pipe in drain and be sure to get good understanding of a tight seal.. then go for it. You can test the whole job next day or two but I have never seen one of these no-calk drains fail if person understands how they work! I think you'll see what I mean.
On the walls... if just 1/8" panels that get adhered to wall then one trick is to install as usual but then after setting panel in place you want to pull it off the wall, let air dry for 3-4 minutes and then readhere the panel. This will help keep panels in place better than if you don't do this.. ;) Don't forget to fill the space we discussed earlier.
Let me know what's next??
MARK
|
|
 |
Full Member
|
|
Sep 3, 2008, 12:59 PM
|
|
Sounds good... what about the dirt down in the hole? Should I throw a small amount of morter down there?
|
|
 |
Senior Plumbing Expert
|
|
Sep 3, 2008, 01:04 PM
|
|
Not necessary as excess mortar will fall in if you space mortar only 4-6 inches away from drain and then set the base (better it fall in and fill this void then to squeeze up through hole).
|
|
 |
Full Member
|
|
Sep 4, 2008, 09:37 PM
|
|
Hey mark,
So I am still here,, still working,, haha
Couple of things... I think I might have messed up, I thought I had enough morter down but after a day, I came back and put some weight on the shower,, and I kind of got a squishy sound and herd some air squeeze out,, :-/
Also I'm worried about the drain,, it seams as though I can't tighten it all the way, it will get so tight then slip out of the threads... and be uneven... maybe I'm just tighting it too much,,
|
|
 |
Senior Plumbing Expert
|
|
Sep 5, 2008, 04:34 AM
|
|
Hi Brian... see if possible to unscrew the pan and see if can pull it up. If not... fine, but if can would be best too and start over.
The slipping of the threads is most likely due to the rubber not being pushed down deep enough into the drain assebly. Take a 1/4" nut driver or similar blunt tool and tap on this with a hammer to see if can set the donut deeper... let me know... ok?
|
|
 |
Eternal Plumber
|
|
Sep 5, 2008, 04:42 AM
|
|
82 answers on this thread! Got to be a new record for a single thread!
|
|
 |
Senior Plumbing Expert
|
|
Sep 5, 2008, 04:49 AM
|
|
Funny stuff huh, Tom. This guy is actually working closely with me and together we're going to finish it!
I'd hire this guy in a heartbeat!
MARK
|
|
 |
Full Member
|
|
Sep 5, 2008, 06:12 AM
|
|
I will see if I can't get it up... actually I stuck my hand down there last night through the open wall side,, and it was still mostly wet... so hopefully I can,, one thing, you said thin set morter was OK right? I thought I remembered you saying it was...
Could I just put some more down over the stuff now? Or should I try to get most of what's there up?
Haha Tom we were going for a record,,
Funny Mark,, I was thinking I should go into plumbing ;)
I always had respect, but this is definetely a new found greatness for Plumbers
Thank you thank you thank you
Have a great day
|
|
 |
Senior Plumbing Expert
|
|
Sep 5, 2008, 07:51 AM
|
|
Brian... try to get it up and clean all... then post back... thinking maybe structolite may be best here (sold at home depot in my area).
Let me know...
|
|
 |
Full Member
|
|
Sep 5, 2008, 09:32 AM
|
|
Got it up easy... wasnt even sticky... wasn't even dry, I don't know if it's the stuff I got or what... its premixed thinset from home depot, it says for tile, will it be OK for the tile??
Anyway I don't think I'll have a problem getting it up, definitely going to go get some structolite... :)
I forgot to say about the seal... I think I am getting it down all the way it looks kind of slanted in the drain also... did I mess it up? Or is it problay just stuck will try again when I reset the shower base.
Talk soon
Thanks mark
|
|
 |
Senior Plumbing Expert
|
|
Sep 5, 2008, 10:20 AM
|
|
Stick with the structolite... stuff dries overnight... see picture below. This is all I use... squeezes out nicely too.
If donut looks crooked then it must not have been set deep enough? Double check the fit again when base is up and then try again.
Let me know...
|
|
 |
Full Member
|
|
Sep 5, 2008, 02:18 PM
|
|
Hey mark,,
Just finished with the structo,, I have to say, that plus the brass drain unit, I feel 100 times better.
:) thanks
|
|
 |
Senior Plumbing Expert
|
|
Sep 5, 2008, 02:52 PM
|
|
That structo-lite is great stuff to work with huh.. Wait'll the morning then let me know what you think...
|
|
 |
Full Member
|
|
Sep 5, 2008, 08:14 PM
|
|
Lol yea it wasn't too bad, I opted for the manual hand mixing... wasn't bad at all, and that brass drain made all the difference, it's a lot better.
So is there a maximum horizontal run for my vent pipe? Because I have a way but it would require an L shape would be 22ft in one direction then a right turn and about another ten ft, then straight up to the roof... is this allowed? Otherwise the other way is a little more complicated.
Let me know
|
|
 |
Senior Plumbing Expert
|
|
Sep 6, 2008, 09:29 AM
|
|
Brian...
You want to take shortest route possible...
As Iamgrowler (on-site plumber) so perfectly posted to me back at an older post... "Most codes allow only 1/3 of a vents overall developed length to be run horizontal. On a vent with a developed length of 60 feet, only 20 feet of that run would be allowed to be horizontal -- If the horizontal run exceeds 1/3 of the developed length, then you must increase the pipe size of the entire vent by one pipe size."
That means that if you go the route you presented that you would need to increase your vent to 2.5" minimum... not readily available either...
OR... find a shorter horizontal route... ;)
Let me know
|
|
 |
Full Member
|
|
Sep 6, 2008, 10:57 AM
|
|
I can do a shorter horizontal route :) I could cut it down to something like 20 ft , then straight up
P.S. That shower base is awesome, its solid :D
|
|
 |
Senior Plumbing Expert
|
|
Sep 6, 2008, 12:01 PM
|
|
:D Back at you!
Keep 'em comin'...
|
|
 |
Full Member
|
|
Sep 6, 2008, 12:50 PM
|
|
So if I were to have a horizontal L at 20ft total that would be OK?
|
|
 |
Senior Plumbing Expert
|
|
Sep 6, 2008, 01:15 PM
|
|
Borderline, but I think this will work just fine for you! Go for it!
|
|
Question Tools |
Search this Question |
|
|
Add your answer here.
Check out some similar questions!
How to fix basment wall leaks
[ 2 Answers ]
I have water coming into my basment through the walls. Mainly where the wall meets the floor. How can I take care of this problem.
Basment not level
[ 3 Answers ]
Hi...
Just bought a house and the basement is not level. What can be done to create a level floor ready for carpeting. How much with labour and material would it cost?
Leaking basment
[ 3 Answers ]
I have a old house with a stone foundation, what's the best way to seal a stone foundation, we are getting leaks from a couple areas.
Thank you
Rob
New bathroom in basment
[ 2 Answers ]
Hello I have a couple of questions, first off I am building a bathroom in my basement. It is a new house only 2 years old there are two stubs in the basement. One is the small one which I am guessing is the toilet the other a large square hole filled in with rock. I am guessing this is for the tub....
Too hot upstairs too cold in the basment!
[ 2 Answers ]
I'm trying to fix a problem in my house. There is only one thermostat and it is on the main floor but heat rises! So upstairs is really hot! In the basement it's really cold! What is the best way to fix this? I am renovating the basement so I would like to fix this before I cover the ducts up. I...
View more questions
Search
|