    Cast iron or PVC drain?
    We are in the process of replacing an all tile shower. The plumber has brought over a new drain kit which is cast iron. The drain in the concrete floor is pvc. And our tile man is concerned about a secure seal since they are two types of material. He is trying to prevent any future leakage which would settle under the shower pan should there be a back-up. Any advice? KD
    Milo Dolezal's Avatar
    Milo Dolezal Posts: 7,192, Reputation: 523
    Plumbing Expert
     
    #2

    Jul 29, 2008, 05:34 PM
    Your tile-man is correct: if you have PVC pipes in the ground - than use PVC trap. But, it is perfectly OK to use Cast Iron shower drain that mounts over PVC riser.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Cast iron drain. [ 4 Answers ]

I'm installing a Bathroom. I want to move the toilet. What should I use to cut the cast iron drain ( 4" ) going into wall? I want to use PVC drain for toilet, sink and shower.

Cast Iron Shower Drain [ 1 Answers ]

Good day, I am in the process of remodeling a bath room and I am at a point where I am not quite sure what to do... I have a cast iron flange with a cast iron riser and shower pan drain in a sunken slab that I would like to replace but with a small extension on the riser to accommodate the new...

Replacing Tub drain into cast iron. [ 1 Answers ]

My tub drain is downstream from both the toilet and the roof vent and every time the toilet flushes the tub trap is emptied and I get sewer smells... Photo @ www3.ns.sympatico.ca/dlpotter/Plumbing/ I think I need to add an anti-siphon device between the trap and the cast iron....

Converting cast iron floor drain to shower drain [ 3 Answers ]

I am adding a bathroom to my basement, which has partial (complete? ) plumbing already roughed into the floor (in 1976). Sewage lift station (vented) is 3 ft from 4" styrofoam plug (toilet), 4 ft from 1 1/2 inch cast male pipe end extending through floor (lav, have already added vertical vent...


View more questions Search