Hello all,
I've been lurking in this forum for a while and I've learned a lot. Thanks to all you experts.
I'm planning a new 1st floor bathroom. I'll be running a new 3" PVC drain line horizontally (1/4" per foot slope) in the basement from the main stack to the new bathroom about 15 feet away.
I've made a sketch of the proposed layout here. The drawing does not show the vents - I'm intending to run 2" vent from both the lav and the washer; they would join in the ceiling and continue 2" up through the roof (this is a new vent in the roof).
Is the toilet and the tub wet-vented properly with this arrangement or should I add more vents. The local code is UPC 2000. Anything else I should be worried about?
Any other suggestions or comments are welcomed. Thanks very much!
Roy