    Construction Accounting
    What costs are included in the builders overhead category?
    RubyPitbull's Avatar
    RubyPitbull Posts: 3,575, Reputation: 648
    Ultra Member
     
    #2

    Feb 12, 2007, 09:28 AM
    --All insurances, for the job (gen liability,. ) & employees (worker's comp, unemplymnt, disabil, medical,. )
    --All GC/owner tax liab for employees
    --if labor is a separate line item being charged, all labor of non job related employees (acctg staff, legal exp for contract write up, job supervision,. ) if labor is not a separate line item, that is included here.
    --clean up expense on a daily basis, which would include materials used.
    --protection of job site (which would include materials used.)

    I am sure I probably missed something.
    Depending on the project, it can be a number of things.

    If you are a client that is asking this question, usually the rule of thumb on charges is the cost quoted plus 10% labor and 10% overhead, cleanup & protection.

    If you are trying to properly figure out what to book in the system and attribute to client, you must look at all items in g/l that are costing the company money, take a percentage of those costs and apply across the board to all jobs.

    If you have a specific concern, please post here and I will try to help you further. :)
    cinlou07's Avatar
    cinlou07 Posts: 2, Reputation: 1
    New Member
     
    #3

    Feb 12, 2007, 10:17 AM
    I am doing a cost certification at the end of the project and it has been a few years since I have done a construction certification. The client has water and sewer bills plus electric bills he wants put on the certification but for the life of me I couldn't recall the catergory it fell under and I don't have utilities as a category.

    Thanks
    RubyPitbull's Avatar
    RubyPitbull Posts: 3,575, Reputation: 648
    Ultra Member
     
    #4

    Feb 12, 2007, 10:26 AM
    Yep. You have the right category, general conditions. It may have been a while, but sounds like you are using the old noggin'!

    And, you are quite welcome. Good Luck! :)
    shd_q's Avatar
    shd_q Posts: 1, Reputation: 1
    New Member
     
    #5

    Nov 25, 2011, 04:27 AM
    What is journal entry for jobwork

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

New Construction [ 8 Answers ]

My mother in-law is building a house in Mexico. I already did the wiring in the house and we have to run the service feeds from the meter 150' away. We have a 200 amp panel and I am going to run it underground on a 2" conduit and are going to use 4/0 aluminum. My question is do I need a breaker @...

Cladogram construction [ 1 Answers ]

Kindly guide me to the process of cladogram construction through an appropriate software avalilable on line. I am using morphological data for such analysis and could not find any suitable software. Your immediate help will be highly appreciated. Thank you

New construction [ 1 Answers ]

We are building a new townhouse in Virginia. Would you recommend copper or pvc piping throughout the home and why. Thank you...

New construction [ 3 Answers ]

I plan to have a house built, and circumstances (financial and otherwise) Necessitate that I assume some of the construction chores such as plumbing, Electrical, floor plan design, and contracting. I'm probably way over my Head on the plumbing task because I've had very little experience. The...

Construction [ 1 Answers ]

How much does it cost to build a parliament in a developing country?


View more questions Search