    High low method to calculate fixed cost
    Suppose you have two levels of activities and costs as follows:
    Highest level of activity is 10,000 lowest is 6,000.
    Highest cost is 35,000 while lowest cost is 27,000.
    Use the high low method to calculate the fixed cost.
    hamzashakaa's Avatar
    hamzashakaa Posts: 161, Reputation: 8
    Junior Member
     
    #2

    Jun 7, 2010, 10:04 AM
    I will not answer your question but here is an example:

    Suppose you have two levels of activities and costs as follows:

    Activity (Machine hours) Total Cost

    1,000,000 $80,000
    2,000,000 $150,000

    Variable cost per unit= Difference between the highest cost and the lowest cost divided by the difference in the highest level of activity and the lowest level
    (150000-80000)/(2000000-1000000)=0.07
    multiply the rate by the hifhest or lowest level of activity. Lets multiply it by the highest level of activity (0.07*2000000)=140000 and deduct the amount from the highest cost (150000-140000)=10000 so the fixed cost is 10000
    jutkasuzana's Avatar
    jutkasuzana Posts: 1, Reputation: 1
    New Member
     
    #3

    Feb 19, 2011, 07:08 PM
    Comment on hamzashakaa's post
    Thank you so much. I read my school book 100 times and still couldn't understand than I read your instructions and it was as easy as possible.
    Theroro's Avatar
    Theroro Posts: 1, Reputation: 1
    New Member
     
    #4

    Jul 11, 2012, 08:51 AM
    variable cost per unit =Highest Cost -Lowest cost/Highest units-lowest units
    = 35,000- 27,000 / 10,000-6,000
    = 8,000 / 4,000
    = $2
    variable cost for producing10,000units will be 10,000*2= $20,000

    total cost =Fixed cost + total variable cost
    using highest activity level I e 10,000 units we substitute the known figures

    35,000=Fixed Cost +20,000

    Fixed Cost =35,000-20000
    =$15,000

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

How to calculate high-low method [ 5 Answers ]

To calculate high-low method, give example

How to use high/low method, to calculate the amount of projected monthly fixed cost [ 1 Answers ]

Production in 2005 for Dingy Daytona Dune Buggies was at its highest point in the month of July when 972 units were produced at a cost of $18,448. The low point in production was in January when only 155 units were produced at a cost of $10,667. The company is preparing a budget for 2006 and needs...


View more questions Search