    net present value
    Project A requires an original investment of $65,000. The project will yield cash flows of $15,000 per year for seven years. Project B has a calculated net present value of $5,500 over a five year life. Project a could be sold at the end of five years for a price of $30,000. (a) Using the proper table below determine the net present value of Project A over a five-year life with salvage value assuming a minimum rate of return of 12%. (b) Which project provides the greates net present value?

    Below is a table for the present value of $1 at compound interest.

    Year 6% 10% 12%
    1 .943 .909 .893
    2 .890 .826 .797
    3 .840 .751 .712
    4 .792 .683 .636
    5 .747 .621 .567

    Below is a table for the present value of an annuity of $1 at compound interest.

    Year 6% 10% 12%
    1 .943 .909 .893
    2 1.833 1.736 1.690
    3 2.673 2.487 2.402
    4 3.465 3.170 3.037
    5 4.212 3.791 3.605
    morgaine300's Avatar
    morgaine300 Posts: 6,561, Reputation: 276
    Uber Member
     
    #2

    Feb 15, 2008, 10:02 PM
    Divide your cash flows into 2 categories. One, those that are lump sums. i.e. where you will get one lump sum amount coming in at some future date. Those are just present values of $1. Two, those that are a series of payments. A series of equal payments at equal times is an annuity. So all series of payments will be figured as an annuity.

    What rate of return do you want?

    Figure the present value of A using the above. Then compare with the original investment. A net present value is the difference between the present value of what you are getting out of the investment, and how much you actually invested.

    They've already given you the present value of B. And you compare the two to see which one is higher.

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Net Present Value [ 1 Answers ]

Beta 0.95 Market risk premium 9% Risk free 5% Project will generate after tax cash flows for $340,000 at yearend after 5 years Investment 1.2 million If the project has the same risk as the firm as a whole. Should Furniture Depot, undertake the project? :confused:

Net present value [ 2 Answers ]

Should we purchase that new copier? Campus Print Shop is thinking of purchasing a new, modern copier that automatically collates pages. The machine would cost $22,000 cash. A service contract on the machine, considered a must because of its complexity, would be an additional $200 per month. The...

Net Present Value [ 1 Answers ]

Your company plans to acquire one of two assets. Asset A costs $162,500, and has expected annual cash savings of $37,500. Asset B costs $225,000, and has expected annual cash savings of $77,500. You'll use straight-line depreciation for both assets over their estimated useful lives of 5 years,...


View more questions Search