    What is the variable overhead spending variance for the month?
    The following standards for variable manufacturing overhead have been established for a company that makes only one product:

    Standard hours per unit of output 5.6 hours
    Standard variable overhead rate $12.00 per hour

    The following data pertain to operations for the last month:

    Actual hours worked 2,600 hours
    Actual variable overhead cost $31,330
    Actual output 400 units

    What is the variable overhead spending variance for the month?

    Choose 1 answer
    A. $100 unfavorable
    B. $130 unfavorable
    C. $163 unfavorable
    D. $250 favorable


    smoothy's Avatar
    smoothy Posts: 25,490, Reputation: 2853
    Uber Member
     
    #2

    Oct 26, 2015, 10:21 AM
    You forgot to cut and paste the work you did and the answer you got as well. Since we don't do your homework for you and you have shown no effort to do it yourself
    mikeyom's Avatar
    mikeyom Posts: 3, Reputation: 1
    New Member
     
    #3

    Oct 26, 2015, 08:35 PM
    This is what I got but it's wrong.

    Spending Variance (AH x AR) - (SH x SR)
    AH = 2,600
    AR = (31330 / 400) = 12.05
    SH = 5.6 x 400 = 2240
    SR = 12

    (2600 x 12.05) - (2240 x 12) = 4450
    paraclete's Avatar
    paraclete Posts: 2,706, Reputation: 173
    Ultra Member
     
    #4

    Oct 27, 2015, 02:46 AM
    The spending variance is the difference between the actual and the standard

    so the actual is 31,330 the standard is 5.6 x 400 x 12 (26880)

    do you think there might be some data missing?
    mikeyom's Avatar
    mikeyom Posts: 3, Reputation: 1
    New Member
     
    #5

    Oct 27, 2015, 08:07 AM
    (2600 x 12.05) - (2240 x 12) = $4,450 Unfavorable.
    However, $4,450 is not one of answer list.

    Choose 1 answer
    A. $100 unfavorable
    B. $130 unfavorable
    C. $163 unfavorable
    D. $250 favorable
    paraclete's Avatar
    paraclete Posts: 2,706, Reputation: 173
    Ultra Member
     
    #6

    Oct 28, 2015, 11:17 PM
    This is why I asked you if there is some data missing

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

The total variance both rate and efficiency for variable overhead? [ 1 Answers ]

Cole Laboratories makes and sells a lawn fertilizer called Fastgro. The company has developed standard costs for one bag of Fastgro as follows: Direct material: standard quantity 20 pounds standard cost per bag $8 Direct labor: standard quantity 0.1 hrs standard cost per bag $1.10 Variable...

Computation of materials, labor, and overhead variances; and overhead variance report [ 3 Answers ]

computation of materials, labor, and overhead variances; and overhead variance report I have to Compute the direct materials cost variance, including its price and quantity variances According to the following question, I calculated the price variance which is = (46500x5.20)-(46500x5)=9300...

Materials, labor, and overhead variances; and overhead variance report? [ 0 Answers ]

Materials, labor, and overhead variances; and overhead variance report Kegler Company has set the following standard costs per unit for the product it manufactures. Direct materials (17 Ibs. @ $4 per Ib.) $

Labor efficiency variance, variable overhead rate variance, variable overhead efficie [ 1 Answers ]

Becton Labs, Inc. produces various chemical compounds for industrial use. One compound, called Fludex, is prepared using an elaborate distilling process. The company has developed standard costs for one unit of Fludex, as follows: Standard Quantity Standard Price or Rate Standard Cost ...

Variable overhead efficiency variance [ 3 Answers ]

I have struggled with this homework problem for a while and still don't get any of the multiple choice answers listed. I have applied the formula : variable overhead efficiency variance= (actual hours x standard rate) - (standard hours allowed x standard rate). I have used the factored formula:...


View more questions Search