    DWV wet lines
    Hello All,

    I am about to piece together my first DWV waste and vent lines. The bathroom was remodeled and enlarged to accommodate a 6' tub in a new location. Since I want to keep all in check with codes for MD, I have a few questions please.
    First off does any one see something terribly wrong with my current set up?
    The problem I think I may encounter is the double 3" sanitary t. the water closet drains into a vent elbow which in turn is connected to the double t, from there it all goes 3 south out to the sewer. I plan on using a 1.3 - 1.6 flow toilet. I could use a 3" single t and reroute the kitchen sink to go from a 1.5 and dump into a vertical 3" which will go into a 3" wye if needed.
    The picture is for demonstration. This is close to the actual waste configuration, but the pipe lengths have been shortened on the water closet. EDIT! After posting this I looked and the photo and realized that the kitchen sink is a no go since the slope will need to go the other way. Would I be OK with my wye idea and a single sanitary t below the toilet?
    Thanks,
    Rob
    [IMG][/IMG]
    lilpoppa's Avatar
    lilpoppa Posts: 118, Reputation: 13
    Junior Member
     
    #2

    Mar 8, 2011, 06:51 PM
    Set up sounds pretty good, only thing to watch is you slope on the horozintal pipes.
    moshetojinx's Avatar
    moshetojinx Posts: 3, Reputation: 1
    New Member
     
    #3

    Mar 8, 2011, 07:26 PM
    Thanks lilpoppa,

    I am afraid that I have some issues with this. The problem is that I only have about 3 feet of clearance before it go's out to the sewer
    massplumber2008's Avatar
    massplumber2008 Posts: 12,832, Reputation: 1212
    Senior Plumbing Expert
     
    #4

    Mar 9, 2011, 05:08 AM

    Hi Moshetojinx...

    I'm afraid lilpoppa missed some stuff here, so hope I caught you in time... ;)

    What comes of the main stack... another bathroom or does this become the vent stack out the roof? Here, if any fixtures connect into the "main stack" fitting then you need to add an 1.5" vent to the shower/tub drain.

    You CANNOT use a sanitary tee fitting on a horizontal drain pipe for a waste fittingso stick with the combination wye fitting or just a wye fitting and a 45 degree fitting for the shower/tub drain... add vent within 3 feet of the PTRAP if, as mentioned above, fixtures connect into the main stack.

    You can connect a 3"x2" sanitary Tee fitting on the 3" vertical for the kitchen sink, but in my opinion, a wye fitting is always better. If you decide to pick the kitchen sink up off the horizontal drain then use a wye or wye combination fitting. Also, although 1.5" is allowed in most states for a kitchen sink, I'd run a 2" drain if possible. Install a 2" cleanout near where the sink connects to the 3" drain if it can be readily accessed and also install a 2" cleanout directly under the kitchen sink. In my area, the cleanouts are required by code, but nver mind that, if the sink ever clogs you will be super happy that they are present!

    Pitch should not be an issue with only 6-7 feet of pipe as you only need 1/4" pitch per foot so you are OK there. The drain/vent pipes should be hung every 4 feet, minimum.

    Finally, where is the bathroom sink drain and how are you planning to vent that? For that matter, how are you connecting all the vents and are you connecting into a vent stack or going out the roof?

    Answer my questions and let me know more here, OK?

    Mark
    moshetojinx's Avatar
    moshetojinx Posts: 3, Reputation: 1
    New Member
     
    #5

    Mar 9, 2011, 05:28 AM
    Comment on massplumber2008's post
    Good Morning Mark,
    First thank you for your thorough answer. The "main stack" only has the bathroom sink going into it and then it vent straight up through the roof at that point. I only have one bathroom on the main floor (cape cod), and may tie into the 3" vertical stack for a 2nd floor bathroom in the future. Per your and others suggestions, I am switching over to wyes on the horizontal and the kitchen sink will take another route. The venting seem to be the easiest of all of this. The bathroom sink is not vented since it is 24" from the 3" main and connects via a 3x1.5x3 sanitary t. The shower is 6 feet from the 3" main vent and has it's own 2" vent which connects to the 3" main in the attic.

    Thanks,
    Rob
    massplumber2008's Avatar
    massplumber2008 Posts: 12,832, Reputation: 1212
    Senior Plumbing Expert
     
    #6

    Mar 9, 2011, 06:25 AM

    Glad to help!

    If you plan to add a bathroom into the 3" main stack in the future then you cannot add the sink into the main stack without adding an additional vent to the sink.

    The toilet vent must stay 2" all the way until it connects into a 2" or larger vent.

    More questions? Let me know, OK?

    I'll pop back in around lunch time or so...

    Mark

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Cost to remove/replace galvanized water lines in walls with copper lines. [ 3 Answers ]

The long water lines have been replaced under the house, but not the lines in the wall. What would the cost be for kitchen, 1 full and one 3/4 bath?

Can a existing wet line with a vent exiting on the upper part of the wet pipe be used [ 2 Answers ]

Can a existing wet line with a vent exiting on the upper part of the wet pipe be used for a 2nd bathroom being contemplated for a 2nd floor farmhouse. Both the wet line and waste vent are both located in the basement. They were installed for a first floor bathroom. Please see attached pictures.

Suddenly wet carpet.no wet vacuum availability [ 3 Answers ]

I have about 2 square feet of carpet that got sodden from leaking "wall event'.. have sopped up with towels but am concerned about mildew etc. I have no wet vac capability Advice?

Reducing allowances for DWV lines [ 1 Answers ]

Hi, I am installing new DWV for a bathroom under UPC. I would like to drain a tub/shower line (1 1/2") to a branch drain line (3") with a 1 1/2":3" coupling. The tub/shower will be vented before it gets to the coupling. Is this allowed under code and/or is it a bad idea for any reason? I think...

Electrical equipment with coax lines connected backfeeding 40-60 volts through lines? [ 4 Answers ]

Hi I have a question for any electricians. I am a cable technician and do installations for Cable,Internet,& Voice in homes. What I have encountered a lot is electrical back-feed coming through the copper coax lines feeding from vcr's and tv's in the house which are plugged into electrical outlets....


View more questions Search