    High low method
    do you know how to solve this question?
    An organisation has the following total costs at two activity levels:

    Activity level (units) 15,000 24,000
    Total costs $380,000 $470,000

    Variable cost per unit is constant in this activity range but there is a step up of $18,000 in the total costs when the activity exceeds 20,000 units.

    What are the total costs at an activity level of 18,000 units?
    jaynelin's Avatar
    jaynelin Posts: 1, Reputation: 1
    New Member
     
    #2

    Jan 16, 2011, 01:08 AM
    VCPU=($470,000-$180,000)-$380,000 / 24000 - 15000 units
    =$8/unit
    FC=$380,000-($8*15000 units)
    =$260,000
    TC@18000 units=$260,000+($8*18000 units)
    =$404,000

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

High-low method [ 1 Answers ]

How would you compute the cost formula for overhead using the high-low method?

High low method. [ 3 Answers ]

Hello, I'll be delighted if help me out with this. My question is all about the high low method, stating it's formula and details of what it's used for.

High -low method [ 0 Answers ]

I Need To Know How To Solve A High Method


View more questions Search