    Dap Out Hole - to fill or not
    I removed an old shower base and will be replacing with tile. I found that there is a dap out hole around the drain pipe. There is no sign of any water coming from the hole or piping. Because I am tiling, I need to prep the floor with a solid base. I've read some other responses on this subject, but nothing with my exact situation. Is filling the hole with flooring cement the correct thing to do, or should I fill the hole with something that can be removed. I guess if there are any issues below the tile work, ripping up the cement is the least of my issues. Any thoughts? Thanks much.
    ballengerb1's Avatar
    ballengerb1 Posts: 27,378, Reputation: 2280
    Home Repair & Remodeling Expert
     
    #2

    Nov 5, 2009, 08:37 PM

    What did you do about the old drain pipe and trap in the dap out?
    LeakyJoints's Avatar
    LeakyJoints Posts: 2, Reputation: 1
    New Member
     
    #3

    Nov 6, 2009, 01:37 PM

    The trap must be under the concrete, because it is not visible. There is a horizontal pipe at the bottom of the dap out. Coming from that pipe is the drain to the old shower. I was going to use that existing pipe as the drain for the new shower.
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #4

    Nov 6, 2009, 01:48 PM
    Quote Originally Posted by LeakyJoints View Post
    The trap must be under the concrete, because it is not visible. There is a horizontal pipe at the bottom of the dap out. Coming from that pipe is the drain to the old shower. I was going to use that existing pipe as the drain for the new shower.
    Something's wrong here. There should be a trap and raiser directly under the old shower drain in the dap-out. If not you'rer going to hafta install one. After you get the trap installed and the trap raiser centered you may fill the dap-out up with tamped dirt to within 3 or 4 inches from the top leaving 2 or 3 inches of the raiser above the floor line and fill the rest with cement. You are now ready to install your shower. Good luck, tom

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Can anything fill the fresh chicken pox hole scars [ 4 Answers ]

Recently, I've got kind of deep holes in my face due to chicken pox. The holes are fresh, so if anything could help fill these holes. I'm sure that if it gets older, nothing can help. So please if someone could help me... plzzzzz

Best way to fill hole by side of house [ 1 Answers ]

My dog dug a hole in flower bed in corner by the side of my house. It is about 1 foot by 1 foot. It fills up with water and will enter my house through the weep holes.. What is the best way to fill the hole?

How to I fill a hole in my yard? [ 2 Answers ]

The previous owners of my house started building a pool. However they never completed it and now I am sitting with the hole in my yard. :( Luckly it is not that deep. :) I think filling it with sand will do, but I don't know what kind of sand will do or if that is the right thing to...

Fill hole in slab? Dap out? [ 17 Answers ]

We have a new house in the Northern Midwest, and underneath a bathtup in the basement a 15 inch square hole has been punched into the slab to allow the drain to exist. I've learned this is a Dap Out. It is currently exposed earth, and the nearest outside wall to this hole is at least 10 feet away....


View more questions Search