I'm looking to install a 100 Amp sub panel in my unfinished basement as the first step in completing my renovations on the lower level. The lower level is approximately 1000 sq ft (office, family/tv room, kids playroom and utility room). Here are a few key facts that might be useful to anyone choosing to help answer my questions:
- Main Panel is 200 Amps (panel and breakers are Murray)
- Run from main to sub panel would be around 35 feet
- I live in NY state (Westchester County to be specific)
- Continuous load sources would be furnace (oil), hot water heater, a wine fridge and drink fridge
- Sump pump exists for the downstairs bathroom
- Office will have two high-end graphic workstations each with 1000 watt power supplies and dual 24-inch monitor setup
- Family/TV room will server as multi-media room with home theater (LCD TV, receiver, blu-ray, Xbox 360, etc)
- Office will also have TV, blu-ray, laser printer and inkjet printer
- Utility room will also run some power tools (table saw, shop vac, etc)
I'm estimating current load (if everything were running at the same time) to be around 75 amps. I know that the changes of everything running at exactly the same time is rare but I've aggressively estimated the load to: 1) ensure that the panel can handle everything that I have to throw at it now or in the future and 2) incorporate any immediate overhead that I haven't anticipated in my planning. Given that -- I thought I would install a 100 amp double-breaker in my main (which has space) to feed the sub panel.
So here are my questions and forgive me if these are stupid or easily answered with a Google search. I've been reading a number of things but there are always some conflicting articles/advice.
1) What gauge wire should I be using to connect the main and the sub? I was thinking #4/3 AWG copper would satisfy the feeder requirement for 100 amps at 90C (running the cable from my main down to the basement panel
2) Does the feeder cable need to be installed in any type of conduit (metal/pvc) to run along the basement wall to the panel location or can it run through the ceiling joints like standard romex?
3) Any restrictions to mounting the sub panel in the wall as opposed to plywood backing on the concrete foundation wall? Advantages/Disadvantages to either approach? I was just thinking the in-wall mounting would be cleaner and I could easily hide it away with a picture frame and not have to go into utility room. I was also hoping to have it near my network panel which I plan to put in the wall as well in the office. Hence this question.
4) Any sub panel manufacturer recommendations?
Thanks in advance for any help.
Joe
|
|
 |
Uber Member
|
|
Aug 10, 2009, 02:52 AM
|
|
My answers follow your questions:
1) What gauge wire should I be using to connect the main and the sub? I was thinking #4/3 AWG copper would satisfy the feeder requirement for 100 amps at 90C (running the cable from my main down to the basement panel
#4-3 plus ground is allowed for a 100 amp residential feeder.
The 90 Deg C column does not apply here.
2) Does the feeder cable need to be installed in any type of conduit (metal/pvc) to run along the basement wall to the panel location or can it run through the ceiling joints like standard romex?
The cable can be pulled through holes drilled in framing members, just use protective nail plates were the cable can be damaged by a piercing nail or screw.
3) Any restrictions to mounting the sub panel in the wall as opposed to plywood backing on the concrete foundation wall? Advantages/Disadvantages to either approach? I was just thinking the in-wall mounting would be cleaner and I could easily hide it away with a picture frame and not have to go into utility room. I was also hoping to have it near my network panel which I plan to put in the wall as well in the office. Hence this question.
A panel can be flush mounted, just leave some method of adding cables later.
4) Any sub panel manufacturer recommendations?
Any major brand is fine, GE, Square D, Siemens.
|
|
 |
New Member
|
|
Aug 10, 2009, 07:38 AM
|
|
Thanks TKRussell.
If I choose to go the route of mounting the panel on plywood, is there a minimum thickness required? Also -- for the portion of the feeder cable that does not run through the floor joists, I'm assuming that needs to be placed in conduit of some sort going from the joists to the panel. Or can I just bring the feeder cable straight into the panel?
Thanks again.
|
|
 |
Uber Member
|
|
Aug 10, 2009, 11:03 AM
|
|
We usually use 3/4" plywood, but 1/2" will work also.
No, the cable does not need to be in conduit where it drops down to the panel.
|
|
 |
New Member
|
|
Aug 10, 2009, 11:08 AM
|
|
Awesome -- thanks again.
|
|
 |
New Member
|
|
Aug 10, 2009, 05:59 PM
|
|
One additional question -- for flush mount sub panel installs -- are there minimum clearance requirements above or below the panel?
|
|
Question Tools |
Search this Question |
|
|
Add your answer here.
Check out some similar questions!
Sub-Panel Installation
[ 3 Answers ]
Hello All!
I currently have a 200 Amp main panel which is full. Five years ago we added a pool and the pool company added a sub-panel on the interior garage wall (back to back from the main panel). The two feeder breakers are 40 amp each. This sub-panel supplies the pool equipment and the...
Installation of electral service panel
[ 3 Answers ]
We are about to get our transformer connected to our 320 meter panel by PUD. From the 320 we are running two lines to two 200 amp panels. We are about to pull the 40/40/20 cable through the conduit. The 2 200 amp service panels are 100 feet apart and 100 ft from the 320. We are told that we need...
Sub-Panel installation
[ 1 Answers ]
I want to install a 100 amp sub panel in a shed located approx. 100' from the main house panel. The shed is a wood work shop where I will be using a variety of power tools from radial arm saw to table top saw. Is the 100 amp panel sufficient? What size wire should I use, I was told 6/3G. I will be...
Main lug panel installation
[ 2 Answers ]
I have spliced into a 220 feed running to my pump house to run power to a playhouse.
There were 3 direct burrial #6 awg cables. When I tracked them I had 2 hot and one Neutral, No ground was ran with them. At the pump house the panels ground bar was grounded by copper and rebar into the earth....
Bathroom or outside Breaker panel installation.
[ 2 Answers ]
I asked this before, but can not find the answer.. I am installing a 150 amp service, and originally was putting the breaker box etc in a 1/2 bath.. and was told, that is not proper.. So, I can install same unit, opposite wall, but will be outside, under a totally dry balcony type place, and I...