Originally Posted by
bella serra
I have struggled with this homework problem for a while and still dont get any of the multiple choice answers listed. I have applied the formula :
variable overhead effeciency variance= (actual hours x standard rate) - (standard hours allowed x standard rate). I have used the factored formula:
variable overhead effeciency variance = std rate( actual hrs -std hrs allowed)
I come up with 360???? What am I doing wrong?
The Litton Company has established standards as follows:
Direct material 3 lbs. @ $4/lb. = $12 per unit
Direct labor 2 hrs. @ $8/hr. = $16 per unit
Variable manuf. Overhead 2 hrs. @ $5/hr. = $10 per unit
Actual production figures for the past year are given below. The company records the materials price variance when materials are purchased.
Units produced 600
Direct material used 2,000 lbs.
Direct material purchased (3,000 lbs.) $11,400
Direct labor cost (1,100 hrs.) $ 9,240
Variable manuf. overhead cost incurred $ 5,720
The company applies variable manufacturing overhead to products on the basis of direct labor hours.
[B] The variable overhead efficiency variance is:
A) $520 F. C) $500 U.
B) $520 U. D) $500 F
Here is what I calculated:
Standard = $5/hr at 1200 hrs... $6000
Actual = $4.77/hr at 1100 hrs... $5720
Therefore using the formula : Standard Rate(Actual hrs - Standard hrs allowed)
5(1100-1200) = -500 or 500F
Am I correct on this?