    Variable overhead efficiency variance
    I have struggled with this homework problem for a while and still don't get any of the multiple choice answers listed. I have applied the formula :
    variable overhead efficiency variance= (actual hours x standard rate) - (standard hours allowed x standard rate). I have used the factored formula:

    variable overhead efficiency variance = std rate( actual hrs -std hrs allowed)

    I come up with 360?? What am I doing wrong?

    The Litton Company has established standards as follows:
    Direct material 3 lbs. @ $4/lb. = $12 per unit
    Direct labor 2 hrs. @ $8/hr. = $16 per unit
    Variable manuf. Overhead 2 hrs. @ $5/hr. = $10 per unit

    Actual production figures for the past year are given below. The company records the materials price variance when materials are purchased.
    Units produced 600
    Direct material used 2,000 lbs.
    Direct material purchased (3,000 lbs.) $11,400
    Direct labor cost (1,100 hrs.) $ 9,240
    Variable manuf. Overhead cost incurred $ 5,720

    The company applies variable manufacturing overhead to products on the basis of direct labor hours.

    [B] The variable overhead efficiency variance is:
    A) $520 F. C) $500 U.
    B) $520 U. D) $500 F
    Criado's Avatar
    Criado Posts: 142, Reputation: 15
    Junior Member
     
    #2

    Jul 18, 2008, 06:30 AM
    Hello Bella,

    Can you show us how you get your answer $360?
    bella serra's Avatar
    bella serra Posts: 2, Reputation: 1
    New Member
     
    #3

    Jul 18, 2008, 02:27 PM
    Quote Originally Posted by bella serra
    I have struggled with this homework problem for a while and still dont get any of the multiple choice answers listed. I have applied the formula :
    variable overhead effeciency variance= (actual hours x standard rate) - (standard hours allowed x standard rate). I have used the factored formula:

    variable overhead effeciency variance = std rate( actual hrs -std hrs allowed)

    I come up with 360???? What am I doing wrong?

    The Litton Company has established standards as follows:
    Direct material 3 lbs. @ $4/lb. = $12 per unit
    Direct labor 2 hrs. @ $8/hr. = $16 per unit
    Variable manuf. Overhead 2 hrs. @ $5/hr. = $10 per unit

    Actual production figures for the past year are given below. The company records the materials price variance when materials are purchased.
    Units produced 600
    Direct material used 2,000 lbs.
    Direct material purchased (3,000 lbs.) $11,400
    Direct labor cost (1,100 hrs.) $ 9,240
    Variable manuf. overhead cost incurred $ 5,720

    The company applies variable manufacturing overhead to products on the basis of direct labor hours.

    [B] The variable overhead efficiency variance is:
    A) $520 F. C) $500 U.
    B) $520 U. D) $500 F
    Here is what I calculated:
    Standard = $5/hr at 1200 hrs... $6000
    Actual = $4.77/hr at 1100 hrs... $5720

    Therefore using the formula : Standard Rate(Actual hrs - Standard hrs allowed)
    5(1100-1200) = -500 or 500F
    Am I correct on this?
    Criado's Avatar
    Criado Posts: 142, Reputation: 15
    Junior Member
     
    #4

    Jul 18, 2008, 07:18 PM
    Your answer is correct but I found a minor error. The error is bolden.

    Actual = $4.77/hr at 1100 hrs... $5720

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Overhead Variance [ 1 Answers ]

Company A uses a standard cost system. Overhead cost information for Product CO for the month of October follows: Total actual overhead incurred $14,750 Fixed overhead budgeted $ 1,800 Total Standard...

Variable Overhead efficiency variable [ 1 Answers ]

Variable overhead is applied in the basis of standard direct labor-hours. If the direct labor efficiency variance is unfavorable, the variable overhead efficiency variance will be? a Favorable b unfavorable c zero d indeterminable