        sizing guide for pex supplies
       
      
    
    
    
                  
        hello again speedball, 
 
so I've decided to tackle my pex plumbing project myself and not shell out $700 to the "I know a guy" guy. From what I've read so far, sizing pex is the same as copper, but I value your input greatly. 
 
I am running supplies for an attic half bath. The total run for hot/cold is about 45 feet (with bends calculated in).  
my question is: I know I should run 3/4" for the cold supply, then tee (3/4 X 5/8 X 1/2) at the toilet and reduce down to 1/2" for the lav (which is about 8 feet downstream). Would I be OK running 1/2' the entire length from basement for the hot (which will originate about 2 feet downstream from H2O heater), or just run 3/4" and reduce to 1/2" prior to the lav?  
 
I am hoping any pressure drop will not be significant enough to notice, also only running 1/2" for the hot will save some cash. 
 
your thoughts would be greatly appreciated, 
 
louie
     
     
    
    
    
    
    
    
  
   | 
 
    | 
        
                
      
       
         
      
      
      
      
        
      
            
      
        
      
      
      
     
         
     | 
 
 
	 
	
		 
	 
 
	
	
		
	
	
  
    
    
    
      
                | 
            
      
              
               Eternal Plumber 
              
              
              
              
       | 
        | 
      
                
               
                
                  
                      Apr 10, 2006, 06:14 AM
                  
                 
       | 
     
     
    
   | 
 
  
    | 
    
    
       
        
        
        
       
    
    
    
    
                  
        Hi Guy, 
"my question is: I know I should run 3/4" for the cold supply, then tee (3/4 X 5/8 X 1/2) at the toilet and reduce down to 1/2" for the lav (which is about 8 feet downstream). Would I be ok running 1/2' the entire length from basement for the hot (which will originate about 2 feet downstream from H2O heater), or just run 3/4" and reduce to 1/2" prior to the lav? " 
 
Let me quote code to you.  All mains to be 3/4" with no more then 3 fixtures  taken off a 1/2" branch.  Your hot line will be just fine if you come off a 3/4" main.  Never heard of a 3/4 X 5/8 X 1/2" tee in plumbing.  Because we figure  the ID of a pipe because of the volume it will carry like 1/2" a AC man will figure the same pipe at 5/8" OD for its radiation factor.    Regards,  Tom
     
     
    
    
    
    
    
    
  
   | 
 
    | 
        
                
      
       
         
      
      
      
      
        
      
            
      
        
      
      
      
     
         
     | 
 
 
	 
	
		 
	 
 
	
	
		
	
	
  
    
    
    
      
                  | 
            
      
              
               Junior Member 
              
              
              
              
       | 
        | 
      
                
               
                
                  
                      Apr 10, 2006, 06:42 AM
                  
                 
       | 
     
     
    
   | 
 
  
    | 
    
    
       
        
        
        
       
    
    
    
    
                  
        "Never heard of a 3/4 X 5/8 X 1/2" tee in plumbing" 
 
sorry tom, was getting ahead of myself. I believe I'm thinking of a 3/4 X 1/2 X1/2 , then one of the 1/2s will be reduced to 5/8 for toilet, the other will continue to lav. That should make more sense. 
 
also, both supplies will be coming off 3/4 mains. Looks like I'll save a few bucks on the hot supply. 
 
as always, thanks a million :D  
 
louie
     
     
    
    
    
    
    
    
  
   | 
 
    | 
        
                
      
       
         
      
      
      
      
        
      
            
      
        
      
      
      
     
         
     | 
 
 
	 
	
		 
	 
 
	
	
		
	
	
  
    
    
    
      
                | 
            
      
              
               Eternal Plumber 
              
              
              
              
       | 
        | 
      
                
               
                
                  
                      Apr 10, 2006, 09:37 AM
                  
                 
       | 
     
     
    
   | 
 
  
    | 
    
    
       
        
        
        
       
    
    
    
    
                  
        
	
		
			
			
				
					  Originally Posted by  atticguy
					
				 
				"Never heard of a 3/4 X 5/8 X 1/2" tee in plumbing" 
 
sorry tom, was getting ahead of myself. I believe I'm thinking of a 3/4 X 1/2 X1/2 , then one of the 1/2s will be reduced to 5/8 for toilet, the other will continue to lav. that should make more sense. 
 
also, both supplies will be coming off of 3/4 mains. looks like i'll save a few bucks on the hot supply. 
 
as always, thanks a million :D  
 
louie 
			
		 
	 
 Hey Louie, 
"then one of the 1/2s will be reduced to 5/8 for toilet," 
  I find two things wrong with this statement. 
1) 5/8ths isn't a reduction from 1/2. 
2) You'll supply the cold water to both lav and toilet off a 3/4"main using  a 3/4 X1/2 X 1/2" tee.  You seem to want to complicate  things by changing the size of the branches.  Am I missing something here?  Regards,  Tom
      
     
    
    
    
    
    
    
  
   | 
 
    | 
        
                
      
       
         
      
      
      
      
        
      
            
      
        
      
      
      
     
         
     | 
 
 
	 
	
		 
	 
 
	
	
		
	
	
  
    
    
    
      
                  | 
            
      
              
               Junior Member 
              
              
              
              
       | 
        | 
      
                
               
                
                  
                      Apr 10, 2006, 12:35 PM
                  
                 
       | 
     
     
    
   | 
 
  
    | 
    
    
       
        
        
        
       
    
    
    
    
                  
        "Am I missing something here?" 
 
Not at all, I was. In my minds eye I was seeing the attachment of a compression stop valve to the stub out as a "conversion/reduction". Which it is not. I was not differentiating between rough in and finish plumbing. Reading back I can see where things went awry. This seems like an issue of misunderstanding and miscommunication on my part. Sorry for the confusion, and thanks for your patience with a novice. :o
     
     
    
    
    
    
    
    
  
   | 
 
    | 
        
                
      
       
         
      
      
      
      
        
      
            
      
        
      
      
      
     
         
     | 
 
 
	 
	
		 
	 
 
	
	
		
	
	
  
    
    
    
      
                | 
            
      
              
               Eternal Plumber 
              
              
              
              
       | 
        | 
      
                
               
                
                  
                      Apr 10, 2006, 02:13 PM
                  
                 
       | 
     
     
    
   | 
 
  
    | 
    
    
       
        
        
        
       
    
    
    
    
                  
        Hry Louie,  No problem. 
I don want to bust yochops but a angle stop, (compression stop valve) is a 1/2 X 1/4" compression stop made by Brasscraft.  Cheers,  tom
     
     
    
    
    
    
    
    
  
   | 
 
    | 
        
                
      
       
         
      
      
      
      
        
      
            
      
        
      
      
      
     
         
     | 
 
 
	 
	
		 
	 
 
 
 
 
     
  
   
  
   
  
  
  
  
  
  
  
  
  
  
  
  
  
  
    | Question Tools | 
    Search this Question | 
   
  
    | 
    
    
    
     | 
    
    
    
    
    
     | 
    
   
   
   
 
Check out some similar questions!
Plumber quote using pex, new supplies to attic
 [ 2 Answers ]
Hello , back again. 
 
After all the away time from country/project, I decided to ask a plumber for a quote on running the supplies for my new attic 1/2 bath. (tapping into lines in basement, running all the way up. The attic bath is adjacent to water wall) also, 1st floor bath water wall is opened...
 
 
Bow Sizing
 [ 2 Answers ]
How does one determine what size bow to buy? I have noticed many lengths and draw distances. I don't want to spend a lot of money on a bow to find out it is not comfortable to use.
 
 
School supplies and clothes
 [ 20 Answers ]
This question maybe should be in the education area, but there are some "emotional" aspects to it so I thought I'd post it here. 
 
My children will be in school very shortly. Two of mine are both starting school, and I'm also currently taking care of 2 nephews and a niece, who are also school age....
 
 
Leesy's Guide To... 
 [ 2 Answers ]
In order to keep myself in practice with web design & development, I'm thinking of writing a few "guides" to some common web design topics.  I was just wondering if anyone has some topics they would like to see something on.  Some examples of what I could do a guide on: 
 
 
Positioning using CSS...
 
 
Power Supplies
 [ 1 Answers ]
Hi, 
 
I'm going to be traveling in the caribean, I'd like to take my laptop and camcorder... does anyone know if I need to purchase a separate power regulator, or do the power supplies attached to most electronics take care of any powe surge or lack thereof 
 
Thank
 
 
 
View more  questions
Search
 
 |