4 Attachment(s)
Adding sub panels and then some.
Hello
I am a fully qualified carpenter/builder from Ontario Canada. I have done a number of my own electrical projects on my past homes and I enjoy the challenge.
I was just surfing the site looking for some ideas on my situation and I was enjoying all the good advice that you well experienced folks were passing along to us that aren't as well experienced.
I thought I would put my problem out there to you folks to see if you have any suggestions as to my best plan of attack. I also thought you might find it interesting as it is a bit from the norm.
Well here goes nothing. More years ago than I care to remember (1986) I moved a factory built 1000 sq. ft. one story home to my country lot Dufferin County, Ontario, Canada.
Normally the homes have a basement but this one was set up on a crawl space. So there is insulation in the floor joists and the joists are covered with aspenite. The original FP 200 AMP panel is in the rear left corner of the house looking from the road and being a crawlspace home most of the circuits are run through the attic.
I built a 1000 sq. ft. Pressure treated basement on the lot and had the house moved on top with a crane as per usual. The basement includes an under the house single car garage. I also built a 325 sq. ft. addition foundation onto the left side of the house that is close to power panel side.
At this time the 1000 sq. ft. part of the house is functioning off the 200 AMP original panel. The addition is framed in but not wired. The basement is not wired as well. At this time I just have some temporary lighting and plugs in these areas.
The 200 Amp meter base is at the street side of the house about one third from the left corner. The meter is feed from via 200 Amp service wire from the transformer on the pole at the street. I installed the meter base and conduit under the floor slab that carries the appropriate wires from the meter to the rear right corner of the basement. The wires come back out of the slab inside the conduit still directly below the original 200 Amp panel that is on the main floor rear wall above. All the wires from the meter through to the original 200 AMP main panel are braided copper.
The wires from below the floor slab feed into a large FP 200 AMP disconnect and then through a 200 AMP Bell distribution box and then on to the original 200AMP panel that has it's own 200AMP main breaker in it. The 200AMP 40 space panel upstairs is getting full and I probably could still get the addition on it and maybe a bit more.
You may ask me why in the heck I did this and it's probably overkill. My reasons were as follows I wanted to be able to add a sub panel in the basement to do the basement, basement exterior lights, garage and possibly the addition (through the crawlspace). I didn't want to disturb the original 200 AMP panel and house wiring and wanted a means of disconnecting the main power so I can put in the future sub panel. And at that time I probably had too much money to spend (HA)
I still have to wire the basement, basement exterior lights, addition and garage.
The basement is going to have a bedroom, rec room, bath room, utility room and possibly a summer kitchen.
The garage may have some 20 amp plugs, lights and a 50 AMP welder's plug.
The existing house has baseboard heating and so will the addition and basement. We don't use the heaters much as the woodstove heats most of the 1000 sq. ft. and the basement is well insulated so at this time a few light bulbs keep it from getting below freezing in the winter time. The basement heaters might be used when the basement is completed.
My plans are to run 100 AMP wire out of the distribution box from the auxiliary connectors to a 125 AMP sub panel with a 100 AMP main breaker. From there I was going to complete the rest of the house wiring as mentioned above.
The installation as installed has a permit and it is approved. I still have to take out a permit for the sub panel and the new wiring.
My questions are as follows.
Does this plan sound feasible and is it the best approach. Should I run the welder breaker out of the 100 AMP sub panel to the garage welder plug? Or should I run the welder wire directly out of the left over connectors in the distribution box to 50 Amp disconnect in the garage the feed the welder from that? The garage is at the far right side of the house.
How should the grounding be done in the sub panel? Should it connect to the ground in distribution box? That ground is connected with the earth ground. The other white 14/2 wire running through the distribution box is just temporary and is feeding the well pump from the main panel until I install the new sub panel in the basement.
Is this system going to be overloaded with the addition of the sub panel, heaters, wiring, welder and maybe a small summer kitchen. The dryer, stove, hot water heater is upstairs on the original panel and there is no plans at this time in a second laundry in the basement.
Also I have read about some scary stories of the problems with the FPE Stab-lok panels and that is what I have as the original main 200 AMP panel. It has the breakers with the prongs not the ones that screw on. I haven't had any problems with the panel yet and the GFI breaker has snapped off when it was supposed to a few times.
Should I worry about this panel and change it out when I do the sub panel or should I let it go and just be concerned about the rest of the new work using some other brand.
I hope you enjoyed my dilemma and I look forward to any advice that you folks may have and be willing to offer. I am not an electrician but a fully qualified carpenter/home builder and am I am always eagar to listen to other people's advice and stories.
Thanks
Yours sincerely
:cool: