Ask Me Help Desk

Ask Me Help Desk (https://www.askmehelpdesk.com/forum.php)
-   Accounting (https://www.askmehelpdesk.com/forumdisplay.php?f=19)
-   -   Calculate Overhead (https://www.askmehelpdesk.com/showthread.php?t=736811)

  • Mar 1, 2013, 07:18 AM
    MamaDude
    Calculate Overhead
    The following information is available at the end of May:
    Balance in WIP/May 1 141800
    Direct Mat'ls cost for May 174500
    Direct labor cost for May 162500
    Overhead applied at rate of 140% of direct labor dollars
    Jobs completed during May:
    Job 84 198780
    Job 85 102520
    Job 86 119450
    Job 87 93150
    Job 88 was not complete at the end of May but 72,400 of materials was charged to job 88's job cost card, how much overhead was applied to job 88?

    I think the amount if $70,000 but I can't figure out how to prove that amount using the above information.

    All help will be greaty appreciated! Thanks!