Beta Distribution / Project Management
#1 - The Beta distribution is used in project management to
a) calculate slack on activities not on the critical path
b) calculate the probability that a project will be completed within its budget
c) calculate pessimistic and optimistic activity times
d) determine which activity should be crashed
e) none of these
#2 - The Beta distribution is used in project management to
a) determine which activity should be crashed
b) calculate the probability that a project will be completed within its budget
c) calculate expected activity times
d) calculate slack for activities on the critical path