A job order cost sheet for Rolen Company is shown below.
A job order cost sheet for Rolen Company is shown below.
Job No. 92 For 2,000 units
Date Direct materials Direct labor Manufacturing Overhead
Beg. bal. Jan. 1 5,184 6,700 5,159
8 6,048
12 7,300 6,059
25 2,042
27 4,100 3,403
13,274 18,100 14,621
Cost of completed job
Direct materials $13,274
Direct labor 18,100
Manufacturing overhead 14,621
Total cost $45,995
Unit cost ($45,995 รท 2,000) $23.00
What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job?
If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year?
Prepare summary entries at January 31 to record the current year's transactions pertaining to Job No. 92.