Gannt chart ,Pert Diagram
The system analysis consulting firm of Flow Associates is working on a
systems design project for Wind and Waves Surfing Gear, Inc.
Description Task Must Follow Expected Time (Days)
Draw Data Flow P None 9
Draw Decision Tree Q P 12
Revise Tree R Q 3
Write up Project S R, Z 7
Organize Data Dictionary T P 11
Do Output Prototype X None 8
Revise Output Design Y X 14
Design Database Z T, Y 5
a. Using the data from the table above, draw a Gantt chart to help Flow
Associates organize its design project.
b. When is it appropriate to use a Gantt chart? What are the
disadvantages? Explain in a paragraph.
c. Create a PERT diagram based on the data above. List all paths and
calculate and identify the critical paths.