Predetermined Overhead Rate
I have a homework question where a company uses predetermined overhead rates to apply manufacturing overhead to jobs. The predetermined overhead rate is based on labor cost in Dept. A and on machine hours in Dept. B. At the beginning of the year, the company made the following estimates:
Dept. A Dept. B
Direct Labor Cost $30,000 $40,000
Manufacturing Overhead $60,000 $50,000
Direct Labor Hours 6,000 8,000
Machine Hours 2,000 10,000
I believe the rate for Dept. B is $5.00 but I haven't been able to figure out the rate for Dept. A. I believe it is either 50% or 200% and I'm leaning toward 50%.
Any help would be appreciated.