I want to pour a concrete pad to use as a base for a low structure to hide my trash cans, from both my neighbors eyes and the racoons that like to chew holes in them.
Here's my idea. Dig down six inches, build the forms and add 2" of gravel and 4" of concrete. This area would be 8' long by 6' wide. Then add more concrete to the rear 3' x 8' area to an additional 2" of thickness. I would use this higher area as the actual base for my trash storage building and the lower 3' in front would be an apron to keep my feet out of the mud. My question - pour them separately or together? If the former roughly how long would it take for the first 4" to stiffen up sufficiently for me to pour the rest? I know the air temperature that day will affect the time but a ballpark figure would help.
I hope I have been clear in my evplanation. Thanks in advance.