How to build a concrete footing
Im planning to build a 50' X 30' shop on my acerage. Because of the cost of concrete Im planning on laying out a concrete footing only and speading 3/4' cruch rock on the inside.
Im not quite sure how to build this footing. So far I would build it like so.
- Remove all top soil until I hit solid clay.
- Drill 8" piles every 8 ft or so
- Build concrete forms 8" wide X 10" deep
- Install Rebar inside pile (4 lenghts)
- Install rebar inside forms (4 lenghts) and connect to piles rebar
- Poor concrete into forms.
Am I on the right track? Do I need the piles? Any advise would be greatly appreciated.
Thanks