  • Oct 20, 2008, 05:38 PM
    Dave Ermeling
    What order do I complete my basement finish project?
    I'm done with framing, plumbing & electrical rough-in, and drywall so what comes after drywall taping? I still have to paint, put a drop ceiling in a section, door installation, trim and flooring. Also, do I install cabinets in the bar area and bath before flooring or after?
    I'm assuming I put down flooring before the toilet flange. Any help would be appreciated.
  • Oct 21, 2008, 04:21 PM
    EMERIL LAGASSE

      1. install cabinets
      2. trim all doors and base
      3. prime all surfaces
      4. caulk / fill nail holes
      5. paint walls, standing trim then base
      6. ceiling grid / tile
      7. flooring and shoe molding
      8. get r done:)
  • Oct 23, 2008, 09:06 PM
    Dave Ermeling

    Emeril, I'm only putting in base cabinets. So I put in the cabinets before flooring? Do I also put in the toilet before flooring or after?
  • Oct 24, 2008, 06:59 AM
    EMERIL LAGASSE
    I would install the cabinet first
    Install the bathroom floor before the toilet:)