Originally Posted by hkstroud
Fill cavity with concrete.
Fill to above bottom edge of step. Use a length of 2x4 to joggle the concrete, just poke it with the 2x4, to cause the concrete to run under the step and settle up against the bottom of the step. Place a 1x4 or 1x5 board flat against the step and push and work it down into the concrete. Allow concrete to firm slightly, remove excess concrete down to bottom edge of board or to with in 1". Allow concrete to dry or almost dry. Remove board, cover concrete with dirt up to bottom edge of step. Might have to prop board if the concrete has not firmed up enough when you remove the excess.