Standard labor hours per unit of output... 8.0
Standard labor rate... $13.10
Actual Hours worked... 4,000
Actual total labor cost... $53,000
Actual output... 400 units
What is the labor efficiency variance for the month? Please explain.
![]() |
Standard labor hours per unit of output... 8.0
Standard labor rate... $13.10
Actual Hours worked... 4,000
Actual total labor cost... $53,000
Actual output... 400 units
What is the labor efficiency variance for the month? Please explain.
(Standard Rate x Standard Time) - (Standard Rate x Actual Time) = Efficiency Variance
or:
(Standard Time - Actual Time) x Standard Rate
Give this a try. If there's a specific part you don't understand, ask about that specific thing.