Can't Figure out ending work in process
The Cutting Department of Groneman Manufacturing has the following production and cost data for July.
Production
1. Transferred out 9000 units
2. Started 3,000 units that are 60% complete as to materials at July 31
Costs
Beginning work in process $0
Materials 45,000
Labor 16,200
Manufacturng overhead 18,900
Materials are entered at the beginning of the process. Conversion costs are incurred uniformly during the process. Determine the equivalent units of production for (1) materials and (2) conversion costs.
I'm having trouble figuring out what the ending work in process is, can anyone help?