1 Attachment(s)
Basement Bathroom Roughin
I have home that is 8yrs old. The basement was roughed in for a toilet only and now I would like to add the shower and sink before closing everything off. The problem is the rough in for the sink and shower do not exist. The toilet is currently about 8' from the main soil stack that comes from the first story.. I believe this is probably a “wet vent”?
If I were to add a shower and sink I will need to tap into the sewer line. To do this I am looking to know if I should use a 2” drain for shower and sink. Or does the shower require 3”? The next question is how to vent everything. I am hoping I can use the same method used for the toilet for the shower. As for the sink, I am thinking this will need to be a studor vent as I do not have an option to vent through the roof. Any suggestions? I have include a rough sketch.
As for busting up the floor, do you have any suggestions for how much room is required to work in this area? How much floor do I need to remove?
Basement bathroom roughin
Thanks for the quick reply. That's awesome. As for the AAV I should still be able to fit this under the sink right? The tee you mentioned just downstream from the trap, does it come of the 2" from under the ground?
The last question is when I take out the concrete, do you have an idea for how wide to make my cuts to get enough room to work with the pipe?
I was thinking of renting a electric or gas power concrete saw with proper ventilation of course. Plus an electric jack hammer..