I'm fixing up a loft above my barn and adding electrical service.
The main panel in my house in 200 amp. I was going to add a 80 amp
Sunpanel in the interior of the barn, drawing off the 200 amp main panel
In the basement of our house. I plan on using an 80 amp double pole breaker
In the main panel, then run the wire to the barn. It's about a 50 ft run in the
Basement, plus another 10 foot from the corner of the house to the barn, so
For 80 amps I was going to run 2/3 romex or 2 ga. Thh (probably the #2 ga. Is
Overkill but the length of the run has me leaning towards using it).
A couple of questions I have:
* My main panel in the basement has plenty of open slots - but they are located
Towards the bottom of the panel - since I'm going to be sucking out 80 amps,
Should I move the currently installed breakers down a few slots and put the
New 80 amp dp breaker up top so the 80 amps doesn't have to travel the
Length of the bus in the main panel (which it would if I just install it at the bottom
Open slot), or does the internal copper bus in the main panel have so much
Ampacity that this is a ridiculous question?
* For the 10-15 feet between the barn and the corner of the house - I can either
A) bury the cable or B) create a boxed in 'umbilical cord' from house corner
To barn where I can run the cable. Which is better?
If I bury it, I'd probably run regular 2/3 romex in basement, then connect it to 2/3 Undergound feeder for the final 10 ft jump to the barn since UF is too stiff and probably costs more to do the whole basement run in - if I do this approach, are there wire nuts I can use to splice together the 2/3 UF and 2/3 romex in a large junct box, or for this size wire do I need some special screw down terminal block? If so what's it called and
Does it mount in a special junction box?
Also, if I bury it, how deep do I have to go? (I live in northeast do I have to go below
Frost line or is that requirement just for water lines, etc).
One more - If I bury it I understand I can't use sheathed UF in a conduit for heat
Concerns - if I just use UF do I simply plop it in the ditch or do I at least put a piece
Of press treated plywood over top of it so some pour soul doesn't stick it with a pick
Axe 20 years from now
Thanks in advance for your answers.