Plumber Quit - Have to finish shower drain myself
This project is converting a garage into two bedrooms and a bathroom. I had the floor raised to match the house and the bathroom is all new plumbing. The problem I am having is what to do with the shower drain. The plumber obviously made the pipe extra tall for when the concrete was poured. I wasn't there when they installed my one-piece lasco shower. The pipe is sticking up above the floor about 1.5 inches. It is also slightly tilted. From what I know it needs to be cut down. I don't know how much of a problem it is that it is tilted. The white plastic drain grate says 'oatey' on it. The black plastic ring goes around the outside of the black pipe and appears to have a threading around it to screw in to something. Any help would be greatly appreciated.
Thanks
Bobby
http://www.wickedclarity.com/webpics/DSC00167.JPG
Sewer Clean out - Glue Caps??
All of my inside and in-wall plumbing passed inspection. However the city inspector for Phoenix, AZ stated the two clean outs just outside the foundation need to be glued. Doesn't this defeat the purpose of having clean outs. I can easily glue them in but feel this could be a major problem later on. Any suggestions?