200 amp service to house, 100 amp serivce to workshop what prep is needed?
We are purchasing a home in Florida (Miami Dade Codes) that was built in the early 60's. There is currently a 150amp fuse box in the house which was originally a 2 bedroom house. We are having the panel upgraded to 200amp and breakers. We are also having new wiring installed for a washer, dryer and hot water heater (never done correctly).
Our roof is MAYBE, 12/2 pitch (very low pitch), and therefore there is not a lot of wiggle room in the attic to get all done, major appliance addition wiring will be routed via conduit outside the house.
We also have a 500 sq ft garage that my husband will utilize for a sheet metal and wood working shop.
We were recommended to upgrade service to 200 amp service and run 100 amp service to garage.
At this time we have a meter that is probably older than dirt outside, the wire running from the meter to the house panel is aluminum and will be changed out.
HERE IS THE QUESTION(S)...
"""Is there a preferred box that we should be installing for our household breaker box at this time?""" We will be doing this in stages and do not want to have to go back and redo something later when we run power to the garage!
I noticed that there are upgrade boxes for the meter which include breakers in them, but those examples also said that there was still a load box in the home for it's service.