Ask Experts Questions for FREE Help !
Ask
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #1

    Mar 10, 2005, 12:25 PM
    Slab Rough-In
    I am embarking a project to remodel a half bath to a full bath on the ground floor of a high ranch. (on slab). After getting a couple estimates on the rough-in plumbing, and seeing that they were more than anticipated, I think I am going to give it a shot. I do most everything….framing, drywall, electrical, etc. and can sweat pipes OK, and recently re-did all of the plumbing in the laundry room, replacing steel with PVC and putting it in the wall. With the help of the pros on this site, I figure I’ll have the answers to some questions I have and will be more confident in tackling this project.

    I am confident with running the supply lines and also the waste lines, however, I am a little unsure with the venting and also “tying” in the new PVC waste lines to the existing cast iron. To make it easier to follow, I have attached a photo of the existing gutted ½ bath….The 4” cast drain is the waste for the upstairs bath/kitchen sinks, tub, and toilet, and also the existing toilet drain in this half bath (or what was anyway). The 2” galv. Steel pipe is a waste pipe for only the lavatory sink that was here originally, and I guess the vent for everything else.



    New bathroom will be twice as big, toilet stays in the same spot, sink is being relocated, and I will add a 32’X 60’ shower.

    I had some preliminary questions about doing the demo/waste rough-in:

    1.) Should I saw cut the trench on the sides 1st with a circular saw/concrete blade and then just jackhammer away?

    2.) I was going to run 2” PVC waste lines (1/4” per foot slope) for the shower & sink. Is this OK do do under the slab, and is there anything I should be aware of like putting something under the pipe or insulating it before I bury and fill the trench w/concrete?

    3.) Since the room is gutted, I figured it would be a good opportunity to replace the waste line of the tub upstairs w/PVC and also remove the lend bends from both the upstairs toilet and the existing one (once I jackhammer the slab). A friend of mine did this recently and had to soften the lead with an acetylene torch to remove it and replace w/ a Ferco “donut” type fitting and PVC closet bend. Should I replace these bends since I am doing the work, or will they last at least another 30-40 years?

    Sorry this is so “long-winded”….the wife is on my back looking to start this project, and has confidence in me to do this (strange) and I just wanted to see if I could get some answers so I could begin the demo phase.

    Thanks

    Jon
    Attached Images
     
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #2

    Mar 10, 2005, 01:40 PM
    Slab Rough-In
    Quote Originally Posted by J Bone
    I am embarking a project to remodel a half bath to a full bath on the ground floor of a high ranch. (on slab). After getting a couple estimates on the rough-in plumbing, and seeing that they were more than anticipated, I think I am going to give it a shot. I do most everything….framing, drywall, electrical, etc., and can sweat pipes OK, and recently re-did all of the plumbing in the laundry room, replacing steel with PVC and putting it in the wall. With the help of the pros on this site, I figure I’ll have the answers to some questions I have and will be more confident in tackling this project.

    I am confident with running the supply lines and also the waste lines, however, I am a little unsure with the venting and also “tying” in the new PVC waste lines to the existing cast iron. To make it easier to follow, I have attached a photo of the existing gutted ½ bath….The 4” cast drain is the waste for the upstairs bath/kitchen sinks, tub, and toilet, and also the existing toilet drain in this half bath (or what was anyway). The 2” galv. steel pipe is a waste pipe for only the lavatory sink that was here originally, and I guess the vent for everything else.



    New bathroom will be twice as big, toilet stays in the same spot, sink is being relocated, and I will add a 32’X 60’ shower.

    I had some preliminary questions about doing the demo/waste rough-in:

    1.) Should I saw cut the trench on the sides 1st with a circular saw/concrete blade and then just jackhammer away?

    2.) I was going to run 2” PVC waste lines (1/4” per foot slope) for the shower & sink. Is this OK do do under the slab, and is there anything I should be aware of like putting something under the pipe or insulating it before I bury and fill the trench w/concrete?

    3.) Since the room is gutted, I figured it would be a good opportunity to replace the waste line of the tub upstairs w/PVC and also remove the lend bends from both the upstairs toilet and the existing one (once I jackhammer the slab). A friend of mine did this recently and had to soften the lead with an acetylene torch to remove it and replace w/ a Ferco “donut” type fitting and PVC closet bend. Should I replace these bends since I am doing the work, or will they last at least another 30-40 years?

    Sorry this is so “long-winded”….the wife is on my back looking to start this project, and has confidence in me to do this (strange) and I just wanted to see if I could get some answers so I could begin the demo phase.

    Thanks

    Jon
    Hi Jon,
    Let me address your questions as they come.

    (1) Should I saw cut the trench on the sides 1st with a circular saw/concrete blade and then just jackhammer away?

    Whatever works for you. I just open up the floor with a jackhammer and do the delicate work with a 15 pound sledge hammer.

    (2)I was going to run 2” PVC waste lines (1/4” per foot slope) for the shower & sink. Is this OK do do under the slab, and is there anything I should be aware of like putting something under the pipe or insulating it before I bury and fill the trench w/concrete?

    2" PVC is fine and if there is a problem with the pitch then 1/8" per foot's acceptable. No support is needed for the pipes, just make sure the trench is packed down and there are no dips. Insulation isn't needed since you will be covering the pipes with dirt and visqueen before pouring the cement patch.

    (3)Since the room is gutted, I figured it would be a good opportunity to replace the waste line of the tub upstairs w/PVC and also remove the lend bends from both the upstairs toilet and the existing one (once I jackhammer the slab). A friend of mine did this recently and had to soften the lead with an acetylene torch to remove it and replace w/ a Ferco “donut” type fitting and PVC closet bend. Should I replace these bends since I am doing the work, or will they last at least another 30-40 years?

    If you have the opportunity I would replace ALL the lead fittings with PVC. I haven't seen lead fittings for 40 years when I worked on a old house up in Tampa. Lead was used back in the 30's, and we went to cast iron in the 40's.

    There will be more questions I'm sure. I can walk you through the lay out and installation if you wish. Good luck on a major undertaking. Tom
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #3

    Mar 10, 2005, 06:29 PM
    Thanks for all the info Tom, it helps out a lot. I’d appreciate it if you’d answer my questions as I have them and as you have time. Just let me know if it gets to be too much and I’ll stop.


    The attached photo shows my plan of attack with the waste lines – 2” PVC - one from shower and one from sink and just T them together and then over to 4” cast iron main to tie into.

    1) Should I increase to 3” after downstream of the T connection?

    The line I drew going up the wall was a continuation of the sink drain, and I intended to run this up through the ceiling and then horizontally through the floor joists in order to tie into the existing 2” steel pipe(see previous post for photo, just to the right of the 4” stack).

    2) Can I do this to vent everything? That’s where my confusion lies, in how plumbing should be vented?

    I don’t follow how my current plumbing is vented. The two toilets, upstairs tub and sinks all drain into the 4” cast pipe, however, I see only one vent on the roof, which doesn't look like 4” cast, but yet looks bigger than 2” steel, I guess I’ll take a trip into the attic to see what it is.

    The 2” steel pipe is only a drain for the sink that was previously here, yet it goes up through the floor.

    3) Does everything upstairs like the sink, tub, and toilet tie in to that 2” steel pipe somewhere in the wall for venting purposes?


    Thanks

    Jon
    Attached Images
     
    tommytman's Avatar
    tommytman Posts: 153, Reputation: 2
    Junior Member
     
    #4

    Mar 10, 2005, 10:24 PM
    This looks pretty good to me but Tom is the expert.

    If all of your fixtures drain to the same main pipe and they all empty into it without being to far away then what you may have is a stack vent which is a vertical drainage stack that carries water but is also vented at the roof... short horizontal branch lines extending from a vertical stack do not require additional venting and are said to be stack vented.

    The picture you drew looks good and I think that the shower line would be considered wet vented in your drawing which is OK from what I have read.

    When you fill in the pipes in the foundation use some sand under the pipes... this will make it so that it does not compact over time...
    tommytman's Avatar
    tommytman Posts: 153, Reputation: 2
    Junior Member
     
    #5

    Mar 10, 2005, 10:27 PM
    Almost forgot. I don't think a tee is a good idea. Use wyes... that way you can run a snake through the lines to clean the pipes and the water will flow better.
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #6

    Mar 11, 2005, 12:35 PM
    Slab Rough-In
    Quote Originally Posted by J Bone
    Thanks for all the info Tom, it helps out a lot. I’d appreciate it if you’d answer my questions as I have them and as you have time. Just let me know if it gets to be too much and I’ll stop.


    The attached photo shows my plan of attack with the waste lines – 2” PVC - one from shower and one from sink and just T them together and then over to 4” cast iron main to tie into.

    1) Should I increase to 3” after downstream of the T connection?

    The line I drew going up the wall was a continuation of the sink drain, and I intended to run this up through the ceiling and then horizontally throught the floor joists in order to tie into the existing 2” steel pipe(see previous post for photo, just to the right of the 4” stack).

    2) Can I do this to vent everything? That’s where my confusion lies, in how plumbing should be vented??

    I don’t follow how my current plumbing is vented. The two toilets, upstairs tub and sinks all drain into the 4” cast pipe, however, I see only one vent on the roof, which doesn't look like 4” cast, but yet looks bigger than 2” steel, I guess I’ll take a trip into the attic to see what it is.

    The 2” steel pipe is only a drain for the sink that was previously here, yet it goes up through the floor.

    3) Does everything upstairs like the sink, tub, and toilet tie in to that 2” steel pipe somewhere in the wall for venting purposes?


    Thanks

    Jon
    Hi Jon, Will this job be inspected?
    Starting with #1.
    (1) 1) Should I increase to 3” after downstream of the T connection?
    The line I drew going up the wall was a continuation of the sink drain, and I intended to run this up through the ceiling and then horizontally through the floor joists in order to tie into the existing 2” steel pipe(see previous post for photo, just to the right of the 4” stack).

    No, leave the drain at 2". The vent off the lavatory must extend at least 6" over the flood rim of the highest fixture,(your sink) before you can revent back. You can't tie back to the 2" galvanized untill you get 6" above the highest fixture that drains into that line. If the kitchen sink has been removed or moved to a new vent then your way will work, otherwise it won't. And speaking of that 2" galvanized Iron drain. The basement lavatory,(sink) was installed using a "S"trap which is outlawed by ALL plumbing codes. It should have had its own vent.

    (2) Can I do this to vent everything? That’s where my confusion lies, in how plumbing should be vented?
    I don’t follow how my current plumbing is vented. The two toilets, upstairs tub and sinks all drain into the 4” cast pipe, however, I see only one vent on the roof, which doesn't look like 4” cast, but yet looks bigger than 2” steel, I guess I’ll take a trip into the attic to see what it is.
    The 2” steel pipe is only a drain for the sink that was previously here, yet it goes up through the floor.

    How far is it from the shower trap to the lavatory drain tie in. Code gives you 5". Again, are we running this for a permit and inspection? The vent layout's going to be fine.

    (3)Does everything upstairs like the sink, tub, and toilet tie in to that 2” steel pipe somewhere in the wall for venting purposes?

    Your upstairs toilets and lavatories are vented through the 4"cast iron and the reason the kitchen is on a separate vent is so he could pick up the basement lavatory off it. It most likely revents back in the attic.

    Thanks for the pictures, they helped a lot. Tom

    If you're willing to change out the basement closet bend I might be able to save you the hassle of attempting to tie the PVC into the 4" cast iron stack vent. Replace the existing closet bend with one that has a 2" threaded heel inlet and connect the drain to that, or one with a 45 degree threaded side inlet, (whichever works best) and screw A 2" PVC male adapter into it and connect direct into the closet bend and from there into the sewer. Also do not use a tee to tie the lavatory drain in. Use a 2" combination wye and 1/8th bend instead.
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #7

    Mar 11, 2005, 01:16 PM
    No, this job will not be inspected, so I guess I'm not concerned too much with the details, I am just aiming for:

    1) Want to make sure everything is done right below the slab so it drains right, and:


    2) Want to make sure venting is adequate enough so there are no gases and everything drains OK w/o "gurgling" or whatever.

    This bathroom will not be used nearly as much as the "main" one upstairs.


    Tom, I do have more pictures and I can make diagrams of them like in the last post but it's frustrating though because the web site only allows 40kb or so I guess, so I have to keep resizing and cutting them down and can only post one at a time.

    Thanks for the help, and I'm sure more questions will be forthcoming .

    Jon
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #8

    Mar 12, 2005, 08:58 AM
    Thanks Tom -

    Now I am pretty much in tune with what I have to do with the PVC waste piping. I may come back to a few details like that fitting you were talking about later.

    I've also been searching and reading other threads in the plumbing forum and found some advice and details you gave that answered some questions I had. I'll do this 1st, because you probably get the same questions over & over again and I imagine it can get annoying at times.


    In the meantime, I did some investigation this morning and cut part of the subfloor so I could look up into the wall better and see where everything leads to. Now I've figured everything out and I don't know if it's looking good.

    l'll clarify everything for you so you have a good idea of the plumbing infrastructure in the house:


    1.) The 4" cast iron stack drains everything upstairs - toilet, tub, kitchen and bathroom sinks, and of course, the toilet down here. It goes up all the way to the roof.

    2) The 2" galv. Steel pipe was only a waste line for the bathroom sink that was previously here (remnants of the trap/drain pipe that connects to it you can see in the photo). This pipe however, does not go to the roof as I previously thought but rather goes up the wall approx. 4-5 feet from the ceiling downstairs and then turns 90 degrees and taps into the 4 "cast iron stack.

    Is this arrangement out of the ordinary? Now I don't know if I can do what I proposed earlier with the venting (see photo below for continuation of above photo for proposed vent route).


    -I really don't want to have to cut & support the vertical section of the 4" cast so I can tie in with my vent.

    -I'd also rather not have to drill holes and run a vent pipe all the way through the wall above the new bathroom sink and into the attic and cut another hole in the roof.

    Hey, but I guess if I want a bathroom and there are no other alternatives, I may have to do one of these!!

    Also, what are your feelings on those "internal" vents (called Studor??) that sit in the wall - is that a good alternative? Are they noisy? Will it "stink" at times? Might I look into that in this situation?

    OK, enough rambling for now... thanks again... I'm sure I'll be back :D

    Jon
    Attached Images
     
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #9

    Mar 12, 2005, 10:20 AM
    Basement Rough In
    Quote Originally Posted by J Bone
    Thanks Tom -

    Now I am pretty much in tune with what I have to do with the PVC waste piping. I may come back to a few details like that fitting you were talking about later.

    I've also been searching and reading other threads in the plumbing forum and found some advice and details you gave that answered some questions I had. I'll do this 1st, b/c you probably get the same questions over & over again and I imagine it can get annoying at times.


    In the meantime, I did some investigation this morning and cut part of the subfloor so I could look up into the wall better and see where everything leads to. Now I've figured everything out and I don't know if it's looking good.

    l'll clarify everything for you so you have a good idea of the plumbing infrastructure in the house:


    1.) The 4" cast iron stack drains everything upstairs - toilet, tub, kitchen and bathroom sinks, and of course, the toilet down here. It goes up all the way to the roof.

    2) The 2" galv. steel pipe was only a waste line for the bathroom sink that was previously here (remnants of the trap/drain pipe that connects to it you can see in the photo). This pipe however, does not go to the roof as I previously thought but rather goes up the wall approx. 4-5 feet from the ceiling downstairs and then turns 90 degrees and taps into the 4 "cast iron stack.

    Is this arrangement out of the ordinary? Now I don't know if I can do what I proposed earlier with the venting (see photo below for continuation of above photo for proposed vent route).


    -I really don't want to have to cut & support the vertical section of the 4" cast so I can tie in with my vent.

    -I'd also rather not have to drill holes and run a vent pipe all the way through the wall above the new bathroom sink and into the attic and cut another hole in the roof.

    Hey, but I guess if I want a bathroom and there are no other alternatives, I may have to do one of these!!

    Also, what are your feelings on those "internal" vents (called Studor??) that sit in the wall - is that a good alternative? Are they noisy? Will it "stink" at times? Might I look into that in this situation?

    OK, enough rambling for now....thanks again.....I'm sure I'll be back :D

    Jon
    Hi jon,

    (1) The 4" cast iron stack drains everything upstairs - toilet, tub, kitchen and bathroom sinks, and of course, the toilet down here. It goes up all the way to the roof.

    Let's not befuddle me any more then creeping old age has already has.
    Sink are only located in the kitchen. Lavatorys are located in the bathrooms.
    When you told me the 2" galvanized was the sink drain I assumed it drained the kitchen sink and the basement lavatory connected with a "S" trap to the kitchen sink drain. Whole new ball game on venting the basement group.

    (2)2" galv. steel pipe was only a waste line for the bathroom sink that was previously here (remnants of the trap/drain pipe that connects to it you can see in the photo). This pipe however, does not go to the roof as I previously thought but rather goes up the wall approx. 4-5 feet from the ceiling downstairs and then turns 90 degrees and taps into the 4 "cast iron stack. Is this arrangement out of the ordinary? Now I don't know if I can do what I proposed earlier with the venting.

    Since we now have a dry vent, the way it revents back to the cast iron is perfectly acceptable and you may tie back the PVC in the basement instead of having to revent 6" above the highest fixture. Just can the trap you made with the two 90's and raise it to run in the floor joists so it connects straight in . Give it 1/8 to 1/4"to the foot slope back to the lavatory and invert a drainage tee to connect the PVC to the galvanized vent.

    (3) -I really don't want to have to cut & support the vertical section of the 4" cast so I can tie in with my vent.

    If you're willing to change out the basement closet bend I might be able to save you the hassle of attempting to tie the PVC into the 4" cast iron stack vent. Replace the existing closet bend with one that has a 2" threaded heel inlet and connect the drain to that, or one with a 45 degree threaded side inlet, (whichever works best) and screw A 2" PVC male adapter into it and connect direct into the closet bend and from there into the sewer. Also do not use a tee to tie the lavatory drain in. Use a 2" combination wye and 1/8th bend instead.

    (4)-I'd also rather not have to drill holes and run a vent pipe all the way through the wall above the new bathroom sink and into the attic and cut another hole in the roof.

    You're going to have to raise the vent over the closet bend to eliminate the trap you designed, so rent a angle drill and a 2 3/4" self feed wood bit and run it through the floor joists.

    (5) Also, what are your feelings on those "internal" vents (called Studor? ) that sit in the wall - is that a good alternative? Are they noisy? Will it "stink" at times? Might I look into that in this situation?

    Studor Spring Loaded Mechanical Vents are used as a last resort when you can't vent any other way. You have a vent that's already in place that's ready to tie to. "SWEET!!!"

    This should clear the way for you to proceed. Cheers, Tom
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #10

    Mar 12, 2005, 11:50 AM
    Good, so what you're saying is essentially it's OK to go with the "vent" plan I laid out from the start...

    I feel better now..

    Sorry about the confusion w/ the terminology, now I've learned something new!

    Also, the picture was just to show the route so it would be easier for you to understand/visualize, I know it obviously won't run diagonally through the joists.

    However, I do have a couple quick questions about the PVC vent pipe routing:

    1) Is it OK to have (3) 90 degree turns from the lavatory location to where I tie-in?
    1st turn - vertical at top of wall, turn 90 perpendicular to joists
    2nd turn - through holes in joists over to "joist bay" where 2" steel is,turn 90
    3rd turn - run pipe in joist bay to 2" steel, turn 90 to tie-in

    2) Since the lavatory will no longer be located in it's old spot and the 2" steel will not be draining anything , can I just cut the 2" steel several inches under the slab, cap it and get rid of most of the vertical section under where the PVC vent will tie in, or should I just leave it alone?

    I'm not sure I understand what you meant in the below statement; aren't I still reventing 6" above the highest fixture, being that I am running the PVC well up above the lavatory and over through the ceiling to the 2" steel?


    Since we now have a dry vent, the way it revents back to the cast iron is perfectly acceptable and you may tie back the PVC in the basement instead of having to revent 6" above the highest fixture.

    Thanks again, I'll probably get started next weekend, rent the jackhammer and go to town!

    Have a great weekend... Jon
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #11

    Mar 12, 2005, 12:40 PM
    Basement Rough In
    Quote Originally Posted by J Bone
    Good, so what you're saying is essentially it's OK to go with the "vent" plan I laid out from the start...

    I feel better now..

    Sorry about the confusion w/ the terminology, now I've learned something new!

    Also, the picture was just to show the route so it would be easier for you to understand/visualize, I know it obviously won't run diagonally through the joists.

    However, I do have a couple quick questions about the PVC vent pipe routing:

    1) Is it OK to have (3) 90 degree turns from the lavatory location to where I tie-in?
    1st turn - vertical at top of wall, turn 90 perpendicular to joists
    2nd turn - through holes in joists over to "joist bay" where 2" steel is, turn 90
    3rd turn - run pipe in joist bay to 2" steel, turn 90 to tie-in

    2) Since the lavatory will no longer be located in it's old spot and the 2" steel will not be draining anything , can I just cut the 2" steel several inches under the slab, cap it and get rid of most of the vertical section under where the PVC vent will tie in, or should I just leave it alone?

    I'm not sure I understand what you meant in the below statement; aren't I still reventing 6" above the highest fixture, being that I am running the PVC well up above the lavatory and over through the ceiling to the 2" steel?


    Since we now have a dry vent, the way it revents back to the cast iron is perfectly acceptable and you may tie back the PVC in the basement instead of having to revent 6" above the highest fixture.Thanks again, I'll probably get started next weekend, rent the jackhammer and go to town!

    Have a great weekend....Jon
    Hi Jon, (1) Is it OK to have (3) 90 degree turns from the lavatory location to where I tie-in?
    1st turn - vertical at top of wall, turn 90 perpendicular to joists
    2nd turn - through holes in joists over to "joist bay" where 2" steel is,turn 90
    3rd turn - run pipe in joist bay to 2" steel, turn 90 to tie-in

    Looks good to me, Just keep the pitch and don't have any traps in the line.

    (2) Since the lavatory will no longer be located in it's old spot and the 2" steel will not be draining anything , can I just cut the 2" steel several inches under the slab, cap it and get rid of most of the vertical section under where the PVC vent will tie in, or should I just leave it alone?

    If you have a way to support the galvanized then you may cut the pipe and cap it off. However you have a dry vent connected to the drainage system that isn't hurting anything by leaving it alone. Some home owners would consider that a definite plus. If you ever wanted to add a fixture, Washer box, laundry tray etc. you would have the drainage and vent already installed. I would just cap off the arm coming off the galvanized and retain it as a option.

    (3) "Since we now have a dry vent, the way it revents back to the cast iron is perfectly acceptable and you may tie back the PVC in the basement instead of having to revent 6" above the highest fixture".

    I'm not sure I understand what you meant in the above statement; aren't I still reventing 6" above the highest fixture, being that I am running the PVC well up above the lavatory and over through the ceiling to the 2" steel?( and it's galvanized iron not steel.)

    Looking at it from that viewpoint you are correct. You are indeed reventing over the top of the highest fixture by reventing over the basement lavatory. However if the kitchen sink were to drain into that pipe,(as I thought it did)you would have had to take the revent 6" above the kitcken sinks rim.

    Did you understand this?
    If you're willing to change out the basement closet bend I might be able to save you the hassle of attempting to tie the PVC lavatory and shower drain into the 4" cast iron stack vent. Replace the existing closet bend with one that has a 2" threaded heel inlet and connect the drain to that, or one with a 45 degree threaded side inlet, (whichever works best) and screw A 2" PVC male adapter into it and connect direct into the closet bend and from there into the sewer. Also do not use a tee to tie the lavatory drain in. Use a 2" combination wye and 1/8th bend instead.

    You have a great week end yourself, Tom
    tommytman's Avatar
    tommytman Posts: 153, Reputation: 2
    Junior Member
     
    #12

    Mar 12, 2005, 08:34 PM
    That 2 inch galvanized pipe (that had the old bath lavatory) is vented by way of connecting to your original stack. From your explanation it is tapped into the 4 inch pipe above all other connections so you can definitely connect to the 2 inch and use it to vent your new lavatory sink like you drew in your pictures. Good luck with this project.

    What kind of shower are you going to put in?
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #13

    Mar 15, 2005, 09:56 AM
    I'm back again!


    Tommytman-

    I’m putting in a 32” X 60” shower….Using the Schluter/Kerdi system (not sure if you’ve heard of it).

    www.schluter.com

    It comes with a sloped/prefab base, curb, 4” square drain, and waterproof membrane that you put over the walls. I am then going to tile the walls and floor.

    Tom – I think I understand that statement you made about tying in at the closet bend... I would get a PVC 3" closet bend (90) with an outlet on it that is 2" so that I can bring my drainage into that and tie in at the toilet location. Correct?


    I have a pretty good idea of doing the DWV piping. I am going to get pipe and fittings tonight, lay it out this week and probably open up the trenches and lay it this weekend.

    As I was discussing earlier, since the ceiling and walls are exposed I am going to replace the upstairs tub drain and lead closet bend. Some questions regarding this:


    Tub - Maybe a strange coincidence, but I noticed the tub overflow has been slightly leaking in the past week, so I am actually going to tackle that first, maybe this weekend also. Seems that the plate on the tub is rusting and one of the screws fell out, so when the shower is running and water gets in the hole, it slowly drips downstairs. I want to replace the overflow, trap, and piping with PVC (see photo), and had these questions:

    1) The threaded closed nipple coming out of the 4" cast is exposed approximately 1 ¼” before it “disappears” into that galv. Elbow. Is this enough pipe to attach a “Fernco” type fitting to and then PVC up to the tub, meaning can I cut the nipple where it goes into the elbow, or should I just cut the galv. On the vertical section above the elbow, attach a “Fernco” and run my PVC from there?

    2) How do I loosen the actual tub drain – from inside the tub?

    Lead Bends

    My friend removed a couple lead bends in his house recently and said he tried to drill all sorts of holes in the lead, tried prying it out, etc. but to no avail. He ended up removing them easily with an acetylene torch to soften the lead

    3) Are there any other “tricks or tips” you might have as far as removing the lead from the packed joint? My father-in-law does have an acetylene torch I can use, but just wondering before hand if there were any other “tricks of the trade.”

    I believe that’s all for now….

    Thanks

    Jon
    Attached Images
     
    tommytman's Avatar
    tommytman Posts: 153, Reputation: 2
    Junior Member
     
    #14

    Mar 15, 2005, 10:23 AM
    Tub - Maybe a strange coincidence, but I noticed the tub overflow has been slightly leaking in the past week, so I am actually going to tackle that first, maybe this weekend also. Seems that the plate on the tub is rusting and one of the screws fell out, so when the shower is running and water gets in the hole, it slowly drips downstairs. I want to replace the overflow, trap, and piping with PVC (see photo), and had these questions:

    1) The threaded closed nipple coming out of the 4" cast is exposed approximately 1 ¼” before it “disappears” into that galv. Elbow. Is this enough pipe to attach a “Fernco” type fitting to and then PVC up to the tub, meaning can I cut the nipple where it goes into the elbow, or should I just cut the galv. On the vertical section above the elbow, attach a “Fernco” and run my PVC from there?
    *************************

    They sell plactic adapters that are threaded. If I understand you right you can remove the nipple and use a PVC threaded adapter and don't need a fernco type adapter.

    Tom
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #15

    Mar 15, 2005, 01:08 PM
    TommyT-

    Yes, I'll do that provided I can back that 40+ year old galv. Nipple out of the cast iron with a pipe wrench. About a year ago I tried to take apart some galv. Pipe under the kitchen sink, and spent about 2+ hours trying to loosen the galv. Couldn't for the life of me and had to cut it with a sawzall and use a rubber boot.
    tommytman's Avatar
    tommytman Posts: 153, Reputation: 2
    Junior Member
     
    #16

    Mar 15, 2005, 01:36 PM
    It seems like a tight spot (restricted access)... but I have had several frozen pipe threads like this one (my house was built in 1968). To get them apart I have placed a 3-4 foot extension on my pipe wrench to get extra leverage and then crank away (I use galvanized pipe to make the extension out of). Maybe use some penetrating fluid the night before.

    Good luck
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #17

    Mar 16, 2005, 06:25 AM
    Quick question-

    Would it be OK to run 1 1/2" PVC for my vent pipe (coming out of the lav thorough the ceiling over to the galvanized), even though the drainage will be 2"?

    Just wondering, not a big deal but it would make drilling holes easier plus the galv. Pipe is actually 1 1/2"

    Tom -

    I got all the PVC last night...I attached a photo of the elbow with the side inlet....although it's a solvent weld inlet and not threaded, this is basically what you were talking about right?

    I got the one with the heel inlet also, but after laying it out I think the "sweep" coming into the side inlet will be "cleaner", meaning less bends.

    Jon

    A
    Attached Images
     
    tommytman's Avatar
    tommytman Posts: 153, Reputation: 2
    Junior Member
     
    #18

    Mar 16, 2005, 08:25 AM
    I don't know what the current code is but I know that my vent lines are 1 1/2 inch.

    Tommy
    speedball1's Avatar
    speedball1 Posts: 29,301, Reputation: 1939
    Eternal Plumber
     
    #19

    Mar 16, 2005, 12:54 PM
    Basement Rough.
    Hi Jon,


    Tom – I think I understand that statement you made about tying in at the closet bend... I would get a PVC 3" closet bend (90) with an outlet on it that is 2" so that I can bring my drainage into that and tie in at the toilet location. Correct? *****Yes*****

    1) The threaded closed nipple coming out of the 4" cast is exposed approximately 1 ¼” before it “disappears” into that galv. Elbow. Is this enough pipe to attach a “Fernco” type fitting to and then PVC up to the tub, meaning can I cut the nipple where it goes into the elbow, or should I just cut the galv. On the vertical section above the elbow, attach a “Fernco” and run my PVC from there?

    2) How do I loosen the actual tub drain – from inside the tub?

    (1) How I would address this would be first soak the threads with WD40 and then cut the pipe off ABOVE the elbo and put a 18" pipe wrench on the hub of the elbo and see what breaks free. This is a win-win situation. If the elbo and nipple breaks free out of the cast iron then you can screw is a Male PVC adapter and convert from there, (how large are the threads in the cast iron tee?) If the elbo breaks free you can put a female adapter on the nipple and convert to PVC from there. If all else fails you can cut the nipple at the elbo threads and use a fernco coupling but that should be your last resort.

    (2) The waste and over flow plate will have to be unscrewed But most of the work will be done outside of the tub. If you want to change out the tub shoe and drain you will have to unscrew the drain from the inside. Note: Unless the drain looks really bad I would leave it.

    Lead Bends

    My friend removed a couple lead bends in his house recently and said he tried to drill all sorts of holes in the lead, tried prying it out, etc. but to no avail. He ended up removing them easily with an acetylene torch to soften the lead**** Are we talking about lead closet bends or cast Iron closet bends with poured lead joints?****

    3) Are there any other “tricks or tips” you might have as far as removing the lead from the packed joint? My father-in-law does have an acetylene torch I can use, but just wondering before hand if there were any other “tricks of the trade.”

    (3) If you're referring to a lead and okum poured joint they do make a tool just for removing lead joints. It's called a lead pick. And looks like a slender chisel that's curved with a sharp edge. But you don't need one of those.
    Take a torch and melt down past the lead ring into the okum or pound a screwdriver into the lead down a inch or so. Now you are under the lead ring and you can began to lever it up and out, working your way around rhe hub until it pulls free.

    Would it be OK to run 1 1/2" PVC for my vent pipe (coming out of the lav thorough the ceiling over to the galvanized), even though the drainage will be 2"?**** Yes, We run our vents 2" but since the vent you're tying into is 1 1/2" that would be fine.****

    I got all the PVC last night... I attached a photo of the elbow with the side inlet... although it's a solvent weld inlet and not threaded, this is basically what you were talking about right? **** The only place you will be using threaded PVC fittings is converting from cast iron to PVC. All else will be glue joints.****


    I got the one with the heel inlet also, but after laying it out I think the "sweep" coming into the side inlet will be "cleaner", meaning less bends.
    **** Your drawing shows the drain from the shower and lavatory as coming almost directly into the heel of the closet bend but if you must use any bends use long sweeps or 45's.***

    Good luck, Tom
    J Bone's Avatar
    J Bone Posts: 15, Reputation: 1
    New Member
     
    #20

    Mar 17, 2005, 07:08 AM
    Upon further inspection (see photo), it appears that the bend is lead, and not cast iron. Is the joint with the cast still a lead and oakum poured joint though? Whatever the case, we'll chisel at it and use the torch if we have to in order to remove it. Likewise with the one below grade if I discover it's the same thing.

    1) Once I remove it, do I just clean up the flange and then use a 4" to 3" Fernco "donut", grease it up, hammer it in there and then just push a piece of 3" PVC in the opening and continue with the bend, flange, etc?

    2) The tub drain is not in horrible shape, but the bathroom upstairs is original and that will be totally gutted within the next 2 years also. I figured I would replace the overflow, drain, and piping since the ceiling is now exposed, thinking that when I do the bathroom uspstairs, hopefully I can attach the overflow from the wall (studs expsoed), and attach the drain from in the tub). Even if this is impossible to do from above, I can still leave a piece of unfinished drywall dowstairs with the screws exposed (sort of like an "access panel), so I can make connections after the new tub is installed.

    What's the best way to remove the drain from inside the tub? Perhaps with needle nose pliers opened up, and then twisted? If its "frozen", would it be OK to make a small cut with a sawzall from above on the drain flange? I have a feeling it ain't going to be easy removing that drain!

    Thanks

    Jon
    Attached Images
     

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Depth below slab surface of sewer rough? [ 1 Answers ]

Speedball or anyone who knows, We are trying to design and build a small pool house that will have a bathroom and some kitchen fixtures. Question I have: To figure out the slab elevation (height), what is the vertical depth below the slab surface that the sewer rough piping must be installed...

Incorrectly placed slab rough-in plumbing [ 2 Answers ]

I have a full bathroom rough-in on a slab in an unfinished area of my house. Unfortunately, I have a concern that the waste pipe for the tub has been misplaced. As the pipes stick directly out of the concrete, This may cause quite an issue for me. I have attached a drawing of my rough-in showing...

Rough in under slab [ 1 Answers ]

Hey Tom, I am currently renovating my mother’s bathroom; it was very out of date. Here’s my problem, she lives on a slab. I was hoping you might be able to tell me if my changes in the plumbing will work. I have attached two pictures, one of the old plan and one of the proposed plan, I have tried...

Rough plumbing in a slab [ 1 Answers ]

I want to install a tub with a center drain, in the basement of my house. We have done the rough plumbing and will soon pour the slab. My plumber tells me that I can not buy a tub with a center drain because of the slab. Is this true? If not how should I set the rough plumbing.

Re:tub on the slab [ 1 Answers ]

Tom, thanks for your help. I am understanding that I would just leave the horizontal run of pipe into the 14"x14" hole and that would leave me enough room for the rest of the plumbing, correct?


View more questions Search