    Overhead costs
    Renteria Company applies manufacturing overhead to jobs on the basis of machine hours used. Overhead costs are expected to total $305,000 for the year, and machine usage is estimated at 125,000 hours.
    For the year, $322,000 of overhead costs are incurred and 130,000 hours are used.


    Compute the manufacturing overhead rate for the year.

    $
    rehmanvohra's Avatar
    rehmanvohra Posts: 739, Reputation: 27
    Senior Member
     
    #2

    Sep 8, 2013, 10:38 PM
    Manufacturing overhead rate:
    Expected overheads/expected usage
    $305,000/125,000
    = $2.44 per hour

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

How do you calculate the overhead application rate for estimated overhead costs? [ 1 Answers ]

How do you calculate the overhead application rate?

Manufacturing overhead costs [ 1 Answers ]

Would depreciation ofn delivery trucks be a period cost or overhead on a Cost of Manufacturing statement?


View more questions Search