    Calculate E.U. of production for materials and conversion cost
    Production Data - Basketballs Units %complete
    WIP 1/1 500 60%
    Units started in prod 1000
    WIP 1/31 600 30%

    Cost Data- Basketballs
    WIP 1/1
    Materials $750
    Conversion Cost 600 $1350
    DM 2400
    DL 1580
    Manf OH 1060



    Calculate the following:
    1. equivalent units of production for materials and conversion cost
    2. unit costs of production for materials and conversion cost
    3. assignment of cost to units transferred out and in process at the end of the accounting period
    morgaine300's Avatar
    morgaine300 Posts: 6,561, Reputation: 276
    Uber Member
     
    #2

    Jul 5, 2009, 08:03 PM

    Please see our guidelines for posting homework problems, as posted at the top of this page in red:
    Ask Me Help Desk - Announcements in Forum : Homework Help

    As an added note, equivalents units gets long and involved, and would be difficult for someone to just try to explain in this format. You're going to need to have at least some work done or ask specific questions about where you're stuck.
    rehmanvohra's Avatar
    rehmanvohra Posts: 739, Reputation: 27
    Senior Member
     
    #3

    Jul 6, 2009, 10:09 PM

    I would agree with Morgaine300. The EPU aspect is quite involved, Your question must state the method of valuation of WIP - weighted average or FIFO. Again, the percentage complete should be separated for materials and conversion costs. I have never produced or seen the production of basket balls, but I feel that the materials enter the beginning of the process, and therefore no WIP materials

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Determinet the Equivalent units of production for materials and conversion costs [ 1 Answers ]

Production costs: 1. Transferred out 8960 units 2. Started 1,100 units that are 40% complete as to converstion costs and 100% complete as to materials at July 31 Costs: Beginning work in process $0 Materials 45,010 Labor 14,080 Manufacturing overhead 18,810

Calculate Materials Price Variance [ 3 Answers ]

Company X has a price standard of $2 per lbs. 5,000 lbs was bought at $2.20 per lbs. The actual quantity used was 5,000 lbs, although the standard quantity for output was 4,500 lbs What is Company X's material price variance?

How to calculate unit cost in a production company [ 1 Answers ]

I need to calculate unit cost for a hollow block production company, can any one help me to find out with the help of excel sheet format, so that I can calculate the unit cost. Reply me ASAP


View more questions Search