    How dig should I deep when laying pavers?
    How deep should I deep before laying pavers. I want a long lasting patio surface that doesn’t get easily damaged because of erosion or floods. I know that digging the base deep enough during installation can help prevent the pavers from shifting as well. However, I need to know just how ‘deep’ is deep enough.
    smoothy's Avatar
    smoothy Posts: 25,492, Reputation: 2853
    Uber Member
     
    #2

    Dec 18, 2013, 06:22 AM
    If you go as deep as your frost ine to start the gravel base.. you will eliminate frost heaving which in itself can wreck your work over time....I'm sure you can get away with less than that however.
    creahands's Avatar
    creahands Posts: 2,854, Reputation: 195
    Ultra Member
     
    #3

    Dec 21, 2013, 12:14 AM
    Most pavers are installed on a gravel/sand base. You would have to dig down about 6 inches plus the height of paver.

    Chuck
    21boat's Avatar
    21boat Posts: 2,441, Reputation: 212
    Ultra Member
     
    #4

    Jan 18, 2014, 05:14 AM
    I see the post is a bit old but for others to see visiting the site Im sure you know the basic layouts but this may help

    Hears what we do on the jobsite in PA and goes from 100 to 0 degrees, plenty of rain, We dig as follows.
    1. Brick finished height is 1” above cut grass then add rest of Paver thickness. .
    2. From bottom of Paver ¾ to 1' for concrete sand.
    3. From bottom of sand min 6”.. 2A modified stone (that's ½ to ¾ limestone with quarry dust mixed in)
    4. From bottom of crushed stone Woven Cloth keeps weeds out

    Dig out that depth and tamp dirt flat. Install woven geo cloth.
    Rough spread crushed stone and mechanically tamp stone (to many home owners use a hand tamper and that's why many walks sink and move Carefully spread rest of crushed stone to its finish height tamp to finish height, this must be fairly accurate.

    Now set your plastic spiked side rail widths. Use this for a guide to spread in the concrete sand. I use a 2by and notch it so the top edges go over and pass the plastic rails and the notched inside of the 2by comes within ¾ inch of crushed stone. This sets you concrete sand bed at perfect height. Be aware the plastic rails are to be 99% perfect in grade and the slopes required for runoff etc.

    Note stone base has to be min 6” wider then borders edges so spikes grip and stay solid, stops border movement. After all this is done its time for the Polymeric sand and agin many screw this up and another reason pavers walk later .

    http://www.techniseal.com/web/faq.php?surface=sand

    Make sure the surface is VERY dry. Liberally apply polymeric sand and sweep at an angle until joints are full. Now use left over woven cloth doubled ( takes two people) and run mechanically plate tamper over brick while other fella pulls woven cloth in front so tamper doesn't chip Pavers. This set that sand tightly. Add more polymeric sand and agin sweep at angle and tamp. All instructions are on the polymeric sand bag wet as required. This gives you a VERY solid walk

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Dig in [ 5 Answers ]

Im sure a lot of folks can relate, but why do I get pleasure out of flossing my gums until they want to almost bleed... the pain is soothing as I dig that string under the gumline...

Leak between deep well and reservoir part of deep well [ 2 Answers ]

I have a leak between the deep well submerisble part of the deep well and the reservoir part of the deep well and losing pressure. I have been dealing with this on a daily basis. I have placed numerous calls to a deep well specialist and he says that I don't have a problem, so who do I call because...

New toilet in old concrete slab - how deep do I dig? [ 1 Answers ]

Hi, I'm moving a toilet about 3 feet in my basement bathroom. I've jackhammered a trench about a shovel-width, but I wonder how much material (dirt) I have to remove to get it ready for the plumber. Help!

How deep to dig water main in Birmingham, AL. For frost line? [ 1 Answers ]

We are building a new house and want to run the water line ourselves. How deep should the line be so as not to freeze in Birmingham, AL.

Laying pavers [ 1 Answers ]

How do I figure how much sand I need to cover 72 square feet of space with 2 inches of sand?


View more questions Search