    Golden Company’s total overhead cost at various levels of activity are presented belo
    Month Machine-Hours Total Overhead Cost
    March 51,000 $210,620
    April 41,000 $184,420
    May 61,000 $236,820
    June 71,000 $263,020

    Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is as follows:


    Utilities (variable) $ 61,500
    Supervisory salaries (fixed) 63,000
    Maintenance (mixed) 59,920

    Total overhead cost $ 184,420


    The company wants to break down the maintenance cost into its variable and fixed cost elements.

    Required:
    1.
    Estimate how much of the $263,020 of overhead cost in June was maintenance cost. (Hint: To do this, it may be helpful to first determine how much of the $263,020 consisted of utilities and supervisory salaries. Think about the behavior of variable and fixed costs within the relevant range.) (Do not round intermediate calculations. Omit the "$" sign in your response.)

    Maintenance cost in June $_________________

    2.
    Using the high-low method, estimate a cost formula for maintenance. (Round the "Variable cost per unit" to 2 decimal places and "Fixed cost" to the nearest dollar amount. Omit the "$" sign in your response.)

    Y = $_____ + $_____X

Check out some similar questions!

Echeverria SA is an Argentinian manufacturing company whose total factory overhead c [ 1 Answers ]

Echeverria SA is an Argentinian manufacturing company whose total factory overhead costs fluctuate somewhat from year to year according to the number of machine-hours worked in its production facility. These costs (in Argentinian pesos) at high and low levels of activity over recent years are given...

Accounting total overhead cost using high-low method? [ 2 Answers ]

ABC Co.'s total overhead costs at various levels of activities (all within the same relevant range) are presented below: Month Flying Hours Total Overhead Costs September 8,000 $ 92,000 October 12,000 $ 106,000 November 16,000 $ 120,000 December 4,000 $ 78,000

The Collins Company forecasts that total overhead for the current year will be $12,00 [ 2 Answers ]

The Collins Company forecasts that total overhead for the current year will be $12,000,000 and that total machine hours will be 200,000 hours. Year to date, the actual overhead is $8,000,000 and the actual machine hours are 100,000 hours. If the Collins Company uses a predetermined overhead rate...

Total Unit product Cost & Overhead cost per unit [ 1 Answers ]

I need some help with trying to figure out how to calculate the overhead cost per unit. I have computed the Activity rate as well as the overhead applied for both products. The following is the info provided: Product / Direct Labor hours / annual prod. / total direct labor hours XR7 0.4DLHs per...


View more questions Search
 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.