    Foundation j bolt retrofit
    House has never had any tie down j bolts on
    The mud sill.
    However concrete blocks are hollow and usually
    They fill down two blocks with mortar and place the
    J bolt in the wet mortar poking up through holes
    You bore in the mud sill.

    Can I cut out the face of the block on one web,
    Put the j bolt in, fill with mortar and trowel flat
    With the face to the block? I would only need to
    Cut one web in one block.
    If this acceptable?
    Comments? :-)
    labman's Avatar
    labman Posts: 10,580, Reputation: 551
    Uber Member
     
    #2

    Aug 29, 2005, 01:28 PM
    I don't see any reason why it shouldn't work. Nothing is easier than doing things the right way originally. My house had the bolts, but no nuts on them. Noah's Ark was built by an amateur. The Titanic was built by professionals.
    Simpleton's Avatar
    Simpleton Posts: 7, Reputation: 1
    New Member
     
    #3

    Aug 30, 2005, 07:49 AM
    I've read that the main job of the bolts is to prevent sideways motion. Lack
    Of nuts wouldn't matter I guess.
    I read a amusing post that said j bolts insure that the top two row of
    Block will be attached to the sill when the house collapses.
    Unless the sill is attached all the way to the footing I cannot see
    That it makes much of a difference.
    Code requires 7" bolt penetration w/i 12" from end of each sill
    Piece and 2" thread protrusion. I think the mud needs to go
    down 18" but I could be wrong.
    So far both houses still standing!
    labman's Avatar
    labman Posts: 10,580, Reputation: 551
    Uber Member
     
    #4

    Aug 30, 2005, 07:54 AM
    I too have wondered just how much good the bolts do. By the way, you can just bash a hole in the block with a hand sledge instead of cutting. The rough edge will make for that much better bonding.
    Simpleton's Avatar
    Simpleton Posts: 7, Reputation: 1
    New Member
     
    #5

    Aug 30, 2005, 12:38 PM
    Well then I have a second part of the question:
    I need to level the house as the foundation has
    Dropped long ago but seems to have finished settling.
    If I jack the house level, Ive read that I can drypack
    The difference atop the blockwall and under the
    Mudsill. Drypack being 2/1 sand portland just damp
    Enough to stay in a ball if you hand squeeze it.
    I want to know how much difference you can
    Make up ? 2 1/" OK?
    Any other ideas to makeup this difference, which
    Is tapered?

Not your question? Ask your question View similar questions

 

Question Tools Search this Question
Search this Question:

Advanced Search

Add your answer here.


Check out some similar questions!

Crankshaft Pully Bolt [ 5 Answers ]

Trying to loosen the crankshaft pulley bolt on a 87 Honda accord. Can't find away to hold the pulley and turn the bolt. Any help would be appreciated.

Moving foundation [ 3 Answers ]

Our house was built in 1977, we are the only owners. Our basement/foundations has cracks on all the walls along the cinderblock foundation. We are waiting for an engineer to access the cost of shoring up the walls. Would this be covered by home owners or is the foundation covered under a warranty...

Foundation [ 1 Answers ]

Hello Can someone tell me what is rubber flashing material. That I put against my brick foundation Thanks

Shower Stall bolt down Drains [ 5 Answers ]

I'm in the process of redoing my shower and have removed all the material from stud to stud and down to the subfloor. I would like to replace the shower stall drain portion that is under the subfloor without ripping out the entire subfloor to get to it. My question is, is the portion of the drain...


View more questions Search