shader
Mar 29, 2007, 06:07 PM
I've read various posts concerning the 10 foot rule where a disconnect is needed at the meter if the load panel is more than 10 feet from the meter. This is of interest to me since I would like to relocate my load panel. Question #1-Am I interpreting this correctly?
Question #2- If using a main breaker load panel, what difference does it make how far the panel is from the meter, as long as the panel is accessible? Or……maybe this was answered and I missed it…….. leads to…..
Question #3-Does this rule apply only if the wires from meter to panel are in the interior of the house? Example-My mother's town home, new construction, four years old, built on a slab, in a Chicago suburb. The main breaker load panel is in the garage, and the meter is located on the opposite exterior wall, appx. 40 feet from the panel. It is a standard meter box used for underground utility feeds, and the sheet metal enclosure has no access points. I did some work in the upper crawl space and didn't seen any feed wires, so I'm assuming the wires from the meter to the box run in/under the slab. Question #4 :confused: No meter disconnect required since the wires not physically in the interior, or could there be local waivers for this type of install?
Question #2- If using a main breaker load panel, what difference does it make how far the panel is from the meter, as long as the panel is accessible? Or……maybe this was answered and I missed it…….. leads to…..
Question #3-Does this rule apply only if the wires from meter to panel are in the interior of the house? Example-My mother's town home, new construction, four years old, built on a slab, in a Chicago suburb. The main breaker load panel is in the garage, and the meter is located on the opposite exterior wall, appx. 40 feet from the panel. It is a standard meter box used for underground utility feeds, and the sheet metal enclosure has no access points. I did some work in the upper crawl space and didn't seen any feed wires, so I'm assuming the wires from the meter to the box run in/under the slab. Question #4 :confused: No meter disconnect required since the wires not physically in the interior, or could there be local waivers for this type of install?