smithjoe1985
Jun 6, 2012, 02:14 PM
Cost of subcontracted work (comparable to direct materials) $ 231,000
Direct staff costs (comparable to direct labor) $ 75,500
Studio overhead (comparable to manufacturing overhead cost applied) $ 120,800
Cost of work completed (comparable to cost of goods manufactured) $ 388,500
--------------------------------------------------------------------------------
What Predetermined overhead rate %
What are the following
Job Cost Sheet
Lexington Gardens Project
Costs of subcontracted work $ ?
Direct staff costs ?
Studio overhead ?
--------------------------------------------------------------------------------
Total cost to January 31 $ ?
Direct staff costs (comparable to direct labor) $ 75,500
Studio overhead (comparable to manufacturing overhead cost applied) $ 120,800
Cost of work completed (comparable to cost of goods manufactured) $ 388,500
--------------------------------------------------------------------------------
What Predetermined overhead rate %
What are the following
Job Cost Sheet
Lexington Gardens Project
Costs of subcontracted work $ ?
Direct staff costs ?
Studio overhead ?
--------------------------------------------------------------------------------
Total cost to January 31 $ ?