View Full Version : When installing a new tub and drain upstairs, is it necessary to cut a hole in the ce


lblblb
Feb 26, 2011, 06:31 PM
Putting in a new bathroom in the upstairs. When putting in the tub and drain, is it necessary to cut a hole in the ceiling below to connect the new drain upstairs. Please help.

Milo Dolezal
Feb 26, 2011, 08:01 PM
It depends how you have set up your rough-in. If done properly than you should be able to connect drain through service door behind the tub. Otherwise, you will have to cut access in the ceiling down below.

argaiu1017
Feb 26, 2011, 10:22 PM
If plumbing is installed with floors opened upstairs then you could prefab waste and overflow before setting tub by taking your center demensions. As an apprentice you would probably open up ceiling anyway. So basically I wouldn't use a panel.

Milo Dolezal
Feb 27, 2011, 11:46 AM
In my area of operation, access door is required. Usually, the door is behind the tub. In some cases, it may be in the ceiling in the garage.

argaiu1017
Feb 27, 2011, 12:45 PM
Milo,
I didn't say it is illegal. That is just the way I do my work without opening walls or ceilings if I don't have to. Thanks