I am installing a rinnai tankless hw heater, nat gas, 199k btus in my home.
In the installation manual it states that it is imperative that the unit has adequate gas supply. They suggest that it has its own 3/4 line to it.
My gas supply line consists of what looks like a 2" pipe coming in through the foundation which reduces down to maybe 3/4 or 1" line to enter the meter, then comes out of the meter 3/4 (or 1" perhaps) and immediately goes to 2".
The 2" pipe goes for 45 ft to where it ends up at the hot water boiler and hot water heater.
There is a 1/2 tap coming right off the 2" for the hw heater (sort of like a 2x2x1/2 T).
About 2 feet after that the 2" reduces to 3/4, which then reduces to 1/2 to feed the boiler.
Where the 2" reduces to 3/4 there is a short 3/4 nipple that was used for the reduction(maybe 4" long). Would it make sense to repalce that 3/4 nipple with a 3/4x3/4x3/4 T to feed the rinnai?
So it would be 2" reduced to 3/4 which would feed the rinnai, then reduce to 1/2 to feed the boiler.
So I guess the question is, would that be adequate supply for the rinnai and boiler if they both were to run simultaneously, or does the rinnai need a 3/4 port right off the 2"?
NOTE: There are two ratings on the boiler, one is 130k btu the other 110. Also, right off the meter where ther pipe is 2" there is a 3/4 tap that goes completely in the other direction that feeds a gas range and dryer.
In the installation manual it states that it is imperative that the unit has adequate gas supply. They suggest that it has its own 3/4 line to it.
My gas supply line consists of what looks like a 2" pipe coming in through the foundation which reduces down to maybe 3/4 or 1" line to enter the meter, then comes out of the meter 3/4 (or 1" perhaps) and immediately goes to 2".
The 2" pipe goes for 45 ft to where it ends up at the hot water boiler and hot water heater.
There is a 1/2 tap coming right off the 2" for the hw heater (sort of like a 2x2x1/2 T).
About 2 feet after that the 2" reduces to 3/4, which then reduces to 1/2 to feed the boiler.
Where the 2" reduces to 3/4 there is a short 3/4 nipple that was used for the reduction(maybe 4" long). Would it make sense to repalce that 3/4 nipple with a 3/4x3/4x3/4 T to feed the rinnai?
So it would be 2" reduced to 3/4 which would feed the rinnai, then reduce to 1/2 to feed the boiler.
So I guess the question is, would that be adequate supply for the rinnai and boiler if they both were to run simultaneously, or does the rinnai need a 3/4 port right off the 2"?
NOTE: There are two ratings on the boiler, one is 130k btu the other 110. Also, right off the meter where ther pipe is 2" there is a 3/4 tap that goes completely in the other direction that feeds a gas range and dryer.