ShaferMike
Jul 22, 2009, 02:53 PM
Have a situation where I need to run an 110 amp 240 volt single phase circuit 1480 feet underground.
I am looking at running direct burial 350 MCM aluminum triplex for the length of the run. By my calculation, I see about a 10.5 % voltage drop which is unacceptable.
I believe the 350 MCM will yield a 10.5% +/- voltage drop while handling the amperage.
Considering using a 3KVA 10% boost transformer to take care of the VD, either at the line or load end.
Wire cost - benefit thing..
Any thoughts ?
Thanks
I am looking at running direct burial 350 MCM aluminum triplex for the length of the run. By my calculation, I see about a 10.5 % voltage drop which is unacceptable.
I believe the 350 MCM will yield a 10.5% +/- voltage drop while handling the amperage.
Considering using a 3KVA 10% boost transformer to take care of the VD, either at the line or load end.
Wire cost - benefit thing..
Any thoughts ?
Thanks