Project C0 C1 C2 C3
A –$36 +$20 +$20 +$20
B – 50 + 25 + 25 + 25
Which project has the higher NPV if the discount rate is 10 percent?
Which has the higher profitability index?
Which project is most attractive to a firm that can raise an unlimited amount of funds to pay for its investment projects? Which project is most attractive to a firm that is limited in the funds it can raise?
A –$36 +$20 +$20 +$20
B – 50 + 25 + 25 + 25
Which project has the higher NPV if the discount rate is 10 percent?
Which has the higher profitability index?
Which project is most attractive to a firm that can raise an unlimited amount of funds to pay for its investment projects? Which project is most attractive to a firm that is limited in the funds it can raise?