I am not sure how to solve this problem.
Utiltiy costs at Service, inc are a mixture of fixed and variable components. Records indicate that utiltiy costs are an average of $0.40 per hour at an activity level of 9,000 machine hours and $0.25 per hour at an activity level of 18,000 machine hours. Assuming that this actaivity is within the relevant range, what is the expecterd total utility cost if the company works 13,000 machine hours?
Utiltiy costs at Service, inc are a mixture of fixed and variable components. Records indicate that utiltiy costs are an average of $0.40 per hour at an activity level of 9,000 machine hours and $0.25 per hour at an activity level of 18,000 machine hours. Assuming that this actaivity is within the relevant range, what is the expecterd total utility cost if the company works 13,000 machine hours?