If I have a factory manufacturing widgets and the goal is to operate the factory at 64% (this allows for 20% growth and 16% contingency), if I have take 9% of the factory down for maintenance, does this 9% come out of growth, contingency, or off the top?

For example, operating at 100% I produce 211 each hour. Allowing for 20% for growth, I produce 169 each hour. I also want to allow for 16% contingency which takes my production down to 134 each hour. Now I find that 9% of my factory must go down for maintenance. Where is the 9% subtracted from?

Thanks.

CaptainForest
Apr 8, 2008, 10:58 AM
I am not quite sure what you are asking.

But if at 100% you can produce 211 units…..

And you normally operate at 64%, that means all you are producing right now is 135

So if 9% goes down for maintenance that would reduce the 135 amount.

So now you are operating at 55% or 116 units.

Therefore I guess to answer your question, it would be off the top as you put it.